Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR18-00077
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 6707 S EISENMAN RD
Project NameGowen Industrial Park Bldg. A
Customer Number 
ePlanReviewYes
Description
[Gowen Industrial Park Building A - UDG ONLY] - Quick Permit
New 8"x25' C-900 Underground Piping with thrust blocks and fittings.

[BLD17-03872]
The fire sprinkler system is used for building area increase and for fire area. To construct a 51,408 square foot building to be used for office, storage, and perhaps fabrication. A total of five (5) tenant spaces separated by potentially 1-hr interior walls with block-out framing for potential future openings will be created. This permit is not intended to establish a Certificate of Occupancy for any tenant or for any portion of this building. Each tenant is required to apply for their own Certificate of Occupancy. Separate permits for racking over 8 feet tall are also required. Work is to include reinforced concrete footings, reinforced concrete tilt-up panels, reinforced concrete slab on grade, recessed concrete floors with dock levelers at some overhead doors, cantilevered canopies, steel columns, open web steel roof girders, open web steel roof joists, steel roof deck, continuous insulation installed on top of the roof deck, a membrane roof covering, skylights, metal screens for roof top mechanical units, roll-up exterior doors, side-hinged swinging exterior doors, steel exterior landings and stairways at the West exit doors, storefront windows, trash enclosures, unoccupied mezzanine above the office area supported by bearing walls, interior nonbearing walls, four toilet rooms accessible to the disabled, and finishes. Special Inspection is required for soil (excavation and compacted fill), concrete footings (including reinforcing steel), concrete tilt-up panels (including reinforcing steel), anchors post-installed in hardened concrete, and steel (including welding). The work is required to comply with the approved drawings, with the Geotechnical Engineer’s recommendations, with the Structural Calculations, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/27/20189/28/20189/28/2018APASS
DetailsJim Page
Final underground supply inspection complete.

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush8/2/20188/2/20188/2/2018PDONE
DetailsJim Page
Underground main line flush complete.

Todd Ketterling is the contact for this flush inspection. He has already coordinated with you and Suez to do this flush this afternoon. We really appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro8/1/20188/2/20188/2/2018ADONE
DetailsJim Page
Hydrostatic test for undergound supply witnessed, no pressure loss observed at riser provided gauge.

Underground hydro Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in3/5/20183/5/20183/5/2018PPASS
DetailsJim Page
Rough to cover inspection for underground supply complete, approved for cover.