INSP-Final Inspection | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Final Inspection | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | FAIL |
Jim Page
|
|
|
Need to install correct heads in non-residential areas as shown on city approved drawings. Head in room 105 to close to wall, repair as needed. Submit as-builts showing changes made to fire sprinkler system.
Leon Taylor is the contact. Phone #: ###-#### Inspection requested via web by Randy Knutson
|
INSP-Final Inspection | 10/25/2018 | 10/26/2018 | 10/26/2018 | A | FAIL |
Jim Page
|
|
|
Repair all noted items mentioned through inpsection on level 3 and 4. Contractor needs to walk remaining floors and fix any deficiencies found.
Leon is point of contact. Phone #: ###-#### Inspection requested via web by Randy Knutson
|
INSP-Final Inspection | 10/24/2018 | 10/25/2018 | 10/25/2018 | P | CANC |
Jim Page
|
|
|
Leon Taylor is point of contact. Phone #: ###-#### >> Inspection requested via web by Randy Knutson Inspection cancelled from web by: Randy Knutson
|
INSP-Final Inspection | 10/18/2018 | 10/23/2018 | 10/22/2018 | P | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Randy Knutson
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2018 | 10/4/2018 | 10/4/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for level 1 complete, all hydrostatic testing for project is complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PART |
Jim Page
|
|
|
Hydostatic test for stanpipe complete, level 1 to be tested at a later date.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2018 | 10/2/2018 | 10/2/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on levls 2, 3 and 4 complete, level 1 and standpipes to be tested at a later date.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | CANC |
Jim Page
|
|
|
Hydrostatic test cancelled per point of contact, inspection request will be scheduled for a later date.
Hydro of full building. Leon Taylor is point of contact. Phone #: ###-#### Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in level 1 corridor complete, approved for cover.
Had to reschedule Tuesday inspection to Wednesday. 1st floor Hall Rough-in. Leon Taylor is the man on site. Phone #: ###-#### Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in | 8/31/2018 | 9/4/2018 | 9/4/2018 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Randy Knutson
|
INSP-Sprinkler Rough-in | 8/23/2018 | 8/24/2018 | 8/24/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on north wing level 1 complete excluding corridor heads, approved for cover, corridor cover is not approved until finish pendant heads are installed and inspected.
All Rooms on North Wing. First floor I believe. Leon Taylor should be on site. Phone #: ###-#### Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on east wing level 1 complete excluding corridor heads complete, approved for cover, corridor cover is not approved until finish pendant heads are installed and inspected.
Rough-In 1st floor East Wing Leon Taylor is on-site. Thanks, Phone #: ###-#### Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in corridors on levls 2, 3 and 4 complete, approved for cover.
2nd.3rd,4th Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 8/14/2018 | 8/15/2018 | 8/14/2018 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in rooms on levels 2, 3 and 4 complete, notated city approved drawings with red in areas approved for cover.
3rd and 4th floor Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/15/2018 | 6/18/2018 | 6/18/2018 | A | FAIL |
Troy Cobbley
|
|
|
Missing the small documents and the hanger clips are missing. Per discussion with the fitter it will be rescheduled
3rd and 4th floor Phone #: ###-#### Inspection requested via web by Matthew Lewis
|