INSP-Final Inspection | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 7/11/2018 | 7/12/2018 | 7/12/2018 | P | CANC |
Jim Page
|
|
|
On order for water supply to fire sprinklers scheduled for 13JULY2018, final inspection for overhead fire sprinklers will be completed then. This request is cancelled.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 6/28/2018 | 6/28/2018 | 6/28/2018 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, hydro will be rescheduled for a later date.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/28/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
|
INSP-Sprinkler Rough-in | 5/9/2018 | 5/11/2018 | 5/11/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids complete, hardlids approved for cover.
Rough in on hard lids Phone #: ###-#### Inspection requested via web by Matthew Lewis
|