INSP-Final Inspection | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Jessica Phone #: ###-####
|
INSP-Final Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | CANC |
Jim Page
|
|
|
No inspection performed for this permit due to time constraints, this request is cancelled per conversation with point of contact.
Please call Dillion Barresi with Stock Construcion Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, city approved drawings/small documents could not be located, city approved drawings and small documents are required for inspection.
Dillion Phone #: ###-####
|
INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | FAIL |
Jim Page
|
|
|
Last inspection performed was on 1NOV2018 which resulted in a fail, no follow inspection has been requested for defecincies noted.
Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 10/29/2018 | 10/31/2018 | 11/1/2018 | P | FAIL |
Jim Page
|
|
|
Provide heads under elevated grated platforms that are missing in areas discussed. Provide head gaurds with baffle in areas that are missing. Correct over spaced heads in areas discussed. Provide heads under boilers and chillers as discussed or provide documentation that is approved by the fire code official allowing the coverage to be deleted. Re-install fire sprinklers under elevated obstructions that was removed for obstruction repair. Re-pipe fire sprinkler heads that are blocked by overehead pipe bracing that obscures spray pattern development. Provide fire sprinkler coverage under obstructions next to roll up doors that exceeds the 48inch measurement.
Submit as-builts to Fire sprinkler Plan Reviewer Tim Frost showing all additions of fire sprinklers and the removal of sway bracing due to Type B soil. Provide fire sprinklers onder combined obstructions in areas as discussed. Verify with general contractor to discuss any other punch list items associated with the walkthorugh from this inspection.
1:00 PM inspection would be preferred. Phone #: ###-#### Inspection requested via web by Chris Gregory
|
INSP-Final Inspection | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection complete, fire sprinkler permit will remain in issued status until project is complete due to possible obstructions needing coverage.
Chris Phone #: ###-####y
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Chris Phone #: ###-####Chris Phone #: ###-####
|