INSP-Final Inspection | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 8/31/2018 | 9/4/2018 | 9/4/2018 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final yet.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 8/30/2018 | 9/4/2018 | 8/31/2018 | A | CANC |
Troy Cobbley
|
|
|
We would like to do it first thing in the morning if possible thanks. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 8/15/2018 | 8/15/2018 | 8/15/2018 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Should be done late morning. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Jim Page
|
|
|
New over-build on the southeast side of building has been filled with insulation, no fire sprinkler upright protection required in area filled with insualtion.
Please call Todd 30 minutes prior to arrival Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on dry system passed
. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PART |
Troy Cobbley
|
|
|
24 hour air test dry system started at 8:00am with 43psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Troy Cobbley
|
|
|
Rough in for the dry system and hydro on dry system passed. Also the two new wet system branchlines passed.
Phone #: ###-#### Inspection requested via web by Sam Ball
|