INSP-Final Inspection | 1/22/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Tony Phone #: ###-####
|
INSP-Final Inspection | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
All tile on the 3rd floor is installed but the path of egress on the second floor and first floor have sprinkler issues which include shipping caps still on pendants and lay-in tile missing. Per Jim the only tampers and flow switches tested have been for the second floor. Tony Phone #: ###-####
|
INSP-Final Inspection | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need all ceiling tile installed prior to a final for the 3rd floor.
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | CANC |
Jim Page
|
|
|
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | DONE |
Jim Page
|
|
|
Fire conference for coverage3 around TV monitors complete, sprinkler will be adjusted for proper coverage around TV monitors.
Tony Phone #: ###-####
|
INSP-Final Inspection | 12/6/2018 | 12/7/2018 | 12/7/2018 | P | FAIL |
Jim Page
|
|
|
TV monitors that are ceiling mounted are obstructing, correct obstruction issue.
Tony Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/15/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 3 complete, level 3 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for level 3 and both standpipes witnessed, no pressure loss observed. All but 7 heads complete at time of hydro, hydro for level 3 is complete.
Hydro on 3rd floor and Hydro for stand pipes in all stair wells. Tony Cetani is the Shilo Foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 3 complete, city approved plans will be notated for areas approved for cover.
Tony Cetani is the contact for this rough inspection. He is needing the inspection on the 2nd floor. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 3 complete, city approved plans will be notated for areas approved for cover.
12 sprinkler heads on 3rd floor. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/4/2018 | 9/4/2018 | 9/4/2018 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping on level 3 complete, a cover inspection for finish drops/sprinklers will be required before finish ceiling can be installed.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2018 | 9/4/2018 | 9/4/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test for level 3 overehad fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Tony Cetani is the contact for this RTC/Hydro inspection. We appreciate your help with this. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|