INSP-Final Inspection | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Sprinkler Rough-in | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number scheduled. No inspection performed. Rudy Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PART |
Jim Page
|
|
|
Pre-set hangers for east side exterior canopy inspected, hanger attachments approved for cover.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit scheduled.
|
INSP-Supply line flush | 5/23/2019 | 5/23/2019 | 5/23/2019 | A | PASS |
Troy Cobbley
|
|
|
Unerground supply line flush witnessed. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line hydro test was witnessed with no pressure loss.
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2019 | 5/21/2019 | 5/21/2019 | A | FAIL |
Troy Cobbley
|
|
|
I started the hydro but the contractor contacted me and stated that it would not pass due to excessive loss.
TROY IS OUR FOREMAN THIS IS AN UNDERGROUND HYDRO Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover.
THIS IS A UNDERGROUND COVER INSPECTION. TROY NELSON IS OUR FOREMAN Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 5/8/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional underground supply line piping that is ok for cover.
Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | PART |
Troy Cobbley
|
|
|
See the approved plans for location where the underground piping is ok for cover. The remaining piping will be scheduled for inspection for tomorrow.
THIS IS AN UNDERGROUND COVER INSPECTION. TROY IS OUR FOREMAN Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 3/14/2019 | 3/14/2019 | 3/14/2019 | P | PASS |
Troy Cobbley
|
|
|
Cover inspection for the in building riser only has passed and piping can be buried.
|