INSP-Final Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Final Inspection | 3/29/2019 | 4/1/2019 | 4/1/2019 | A | PEND |
Jim Page
|
|
|
Previousl;y noted items have been corrected, final fire sprinkler inspection complete.
Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | FAIL |
Jim Page
|
|
|
Numerous overspaced issues throughout building next to kitchen, relocate hedas as discussed. Numerous heads to close to registers in restrooms, relocate head or provide intermediate temperature head in discussed locations. Provide heaqd box with required amount and style of heads.
Gerardo Arce is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/29/2018 | 10/29/2018 | 10/29/2018 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, overehad fire sprinkler piping rough in complete, overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2018 | 10/29/2018 | 10/29/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on levels 1, 2 and 3 witnessed, no pressure loss observed at riser provided gauges. Noted that glycerin anti-freeze was used to complete hydrostatic test.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/2/2018 | 10/3/2018 | 10/3/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on levels 1 and 2 complete, levels 1 and 2 approvbed for cover. Rough in inspection for level 3 complete, tenting still needs to be installed, level 3 not approved for cover.
Phone #: ###-#### Inspection requested via web by Stan Beus
|