INSP-Final Inspection | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Ron Phone #: ###-####
|
INSP-Final Inspection | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | PART |
Jim Page
|
|
|
Partial final inspection for fire sprinkler system complete, flow switch currently reports in 7 seconds due to backflow issues, Backflow is going to be changed to allow a longer time frame for flow switch activation. Dry system trip will be completed after backflow is changed.
Gary Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2018 | 12/21/2018 | 12/21/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test for dry system witnessed, no pressure loss observed. 24 hour air test still needs to be performed.
Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2018 | 12/19/2018 | 12/19/2018 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact.
Hydro on the dry system. Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2018 | 12/12/2018 | 12/12/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for remaining overhead wet system fire sprinkler piping witnessed, no pressure loss observed, hydrostatic test for all of wet system complete.
Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Jim Page
|
|
|
Rough in inspection for dry system complete.
dry system Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2018 | 12/7/2018 | 12/7/2018 | A | CANC |
Jim Page
|
|
|
Inspextion request cancelled per conversation with Ron Larson.
Tony is point of contact, ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, visible leaks in a couple of locations, request is rescheduled.
Tony is point of contact, ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2018 | 12/5/2018 | 12/5/2018 | P | PART |
Jim Page
|
|
|
Rough in inspection complete for overehad fire sprinkler piping east of the chapel complete, discussed areas for sway brace attachment, hydro for installed section will be completed on 06DEC2018 per conversation with sprinkler fitter on project.
Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2018 | 12/4/2018 | 12/4/2018 | P | CANC |
Jim Page
|
|
|
Inspection request was suppose to be scheduled for 05DEC2018 per conversation with point of contact. This request is cancelled and will be rescheduled by POC.
Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | FAIL |
Troy Cobbley
|
|
|
Sesmic Restraints needed
Sesmic Bracing incorrect based on drawing. (This item will be consulted with the assitant fire marshal next week.)
Face Bushing OK
Side walls off the wall to be verified by Ron based on manufactuer
As builts are to be provided at the end of the project.
|
INSP-Sprinkler Rough-in | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for locations/rooms in the east half of the basement that was inspected today. As-builts are required, approval is needed for supplying the pendants in the corridor from a 1 1/2" branchline instead of the 3" main, verification is needed for combustible concealed spaces above the ceiling as discussed, need verification of spacing of sidewall heads from the walls they are installed against, need branchline restraints, need earthquake bracing installed, need flat faced bushing changed.
Basement // Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | CANC |
Jim Page
|
|
|
Inspection request rescheduled per conversation with point of contact, inspection request will be rescheduled for 06NOV2018.
Basement // Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2018 | 10/24/2018 | 10/24/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test for basement overhead firte sprinkler piping witnessed, no pressure loss observed.
basement // Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | PART |
Jim Page
|
|
|
Hydrostatic terst for overhead fire sprinkler piping in chapel/sanctuary section complete, remianing sprinkler piping to have hydrostatic test completed at a later date.
sanctuary- Ron Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/10/2018 | 10/11/2018 | 10/11/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with pink highlighter/red ink areas approved for cover.
Ron Phone #: ###-####
|