INSP-Final Inspection | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, overhead system is on dedicated fire line, no irrigation shut down on flow switch activation required.
Jeremy Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/12/2019 | 4/12/2019 | 4/12/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for undergorund supply witnessed, no pressure loss observed.
|
INSP-Sprinkler Rough-in | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, rough to cover inspection for overhead fire sprinkler piping complete, all piping approved for cover.
John Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/15/2018 | 10/16/2018 | 10/16/2018 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, fire sprinkler piping between conditioned spaces approved for cover, piping in attic type spaces cannot be covered until tenting is installed and passed inspection.
John Phone #: ###-####
|