INSP-Final Inspection | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | PASS |
Jim Page
|
|
|
Final inspection for undergound supply complete.
Flushing is scheduled with Stacie of Suez at 10:00 am Tuesday morning. Confirm and cordinate with Troy Nelson ###-#### Phone #: ###-#### Inspection requested via web by Christophe Wilson
|
INSP-Supply line flush | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Flushing is scheduled with Stacie of Suez at 10:00 am Tuesday morning. Confirm and cordinate with Troy Nelson ###-#### Phone #: ###-#### Inspection requested via web by Christophe Wilson
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2018 | 10/23/2018 | 10/23/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground supply hydro test passed
|
INSP-Sprinkler Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Jim Page
|
|
|
Thrust blocks have been poured, rough to cover inspection for undergorund supply complete, approved for cover.
|
INSP-Sprinkler Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PART |
Troy Cobbley
|
|
|
The underground supply line piping is ok to cover except where the thrust blocks need poured. A separate inspection will need to be scheduled for the thrust blocks. Per contractor the underground supply line depth has been verified with laser/gps
Coordinate Underground Inspection With Troy Nelson Phone #: ###-#### Inspection requested via web by Christophe Wilson
|