INSP-Final Inspection | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet. This inspection is for a sprinkler rough-in. See the city approved plans additional heads where piping is ok for cover. I noted on pendant that still needs changed to quick responce and verification that the extended coverage heads can be used in a Storage Room.
Contact Hunter Anderson ###-#### 30 min prior to TCO/Final Insp start please Hunter prefers an early AM inspection if possible
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 11/19/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas marked "ok" where the piping is ok for cover.
Contact Hunter Anderson ###-#### 30 min prior to RTC insp Start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | P | CANC |
Troy Cobbley
|
|
|
Contact Hunter Anderson ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Final Inspection | 8/15/2019 | 8/16/2019 | 8/16/2019 | P | PART |
Jim Page
|
|
|
Previously noted items for phase 2 complete, final fire sprinkler inspewction for phase 2 complete.
Contact hunter Anderson ###-#### 30 Min prior to Final Insp Phase 2 start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 8/14/2019 | 8/15/2019 | 8/15/2019 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for completion of the phase 2 work. I noted one pendant overspaced in an office, one pendant too close to a wall in another office and one exam room where a standard esponce pendant had been left with a new quick responce pendant. HC Company is going to remove a door that is causing an obstruction in a corridor.
Contact Hunter Anderson ###-#### 30 min prior to Final Insp of Phase 2 start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/18/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Troy Cobbley
|
|
|
The piping at the two heads in the west side corridor is ok for cover.
Contact Noemi Carrero ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas marked ok where piping is ok for cover.
Contact Taigen Hines ###-#### 30 min prior to RTC insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/17/2019 | 7/17/2019 | 7/17/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional rooms marked "ok" where piping is ok for cover.
Contact Noemi Carrero - ###-#### 30 Min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans with areas marked "ok" where piping is ok for cover.
Contact Noemi Carrero - ###-#### 30 Min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/15/2019 | 7/16/2019 | 7/16/2019 | P | CANC |
Troy Cobbley
|
|
|
Contact Noemi Carrero ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/10/2019 | 7/11/2019 | 7/11/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for rooms marked "ok" where piping can be covered.
Contact Noemi Carrero ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in rooms 109 and 256 complete, hardlids approved for cover.
Contact Noemi Carrero - ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | CANC |
Jim Page
|
|
|
Contact Noemi Carrero ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Final Inspection | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | PART |
Troy Cobbley
|
|
|
Phase 1 work complete.
Contact Hunter Anderson ###-#### - Fire Final per Troy Cobbley
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 2/27/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Troy Cobbley
|
|
|
Phase 1 area work is complete except one existing pendant needs deleted as discussed and plan review needs to approve leaving the existing pendnat supplied from the dry system as previously discussed.
Please call Hunter 30 minutes before inspection. Thank you, Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Troy Cobbley
|
|
|
The pendant heads in the corridor have been modifed and the piping can be covered. See the city approved plans for these additional heads marked "ok"
Contact Tanner Loomis - ###-#### 30 min prior to RTC iInsp Start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/29/2019 | 1/29/2019 | 1/29/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for pendant heads marked "ok" where piping can be covered. I noted several pendants that are overspaced and will need adjusted. I defered the existing pendants fed from the dry system being removed or left installed to plan review.
|
INSP-Sprinkler Rough-in | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | CANC |
Troy Cobbley
|
|
|
Contact Tanner Loomis ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/28/2019 | 1/29/2019 | 1/28/2019 | A | CANC |
Troy Cobbley
|
|
|
Contact Tanner Loomis ###-#### 30 min prior to RT Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | CANC |
Troy Cobbley
|
|
|
Contact Tanner Loomis ###-#### - 30 min prior to RTC Insp Start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/11/2019 | 1/14/2019 | 1/14/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" where sprinkler piping is ok for cover.
Contact Hunter Anderson ###-#### 30 Min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|