INSP-Final Inspection | 4/19/2019 | 4/19/2019 | 4/19/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkker inspection complete.
|
INSP-Final Inspection | 4/11/2019 | 4/16/2019 | 4/16/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need forward flush test and the fire alarm permit scheduled to test interconnection with fire riser devices.
Please call Jeff with time frame this will include alarm testing and our remaining items. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Conference | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | DONE |
Jim Page
|
|
|
A second curb valve was installed after SUEZ valve to accomplish underground hydrostatic test, underground held 200psi for 2 hours as required by NFPA 13.
This is inspection to confirm our isolation of the underground from the Suez service and hydro test of UG. It can be completed during hydro test for overhead. We will be on site. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply and overhead fire sprinkler piping witnessed, no pressure loss observed.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | FAIL |
Troy Cobbley
|
|
|
The underground supply piping was not pressurized when I arrived at job site. Per Tom a letter from Suez will be provided since the underground piping will not hold pressure. underground // Tom Phone #: ###-####
|
INSP-Supply line flush | 3/14/2019 | 3/14/2019 | 3/14/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | PASS |
Troy Cobbley
|
|
|
Bury depth has been corrected. Underground supply piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Supply line flush | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | PART |
Troy Cobbley
|
|
|
The portion of the supply piping near the Suez connection point is not buried deep enough and will need to be modified and re-inspected. After the second 45 degree elbow the piping is deep enough and can be buried.
Note:Pouring Thrust Block by noon. P Lease see Troy Nelsen Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 2/11/2019 | 2/11/2019 | 2/11/2019 | P | PASS |
Troy Cobbley
|
|
|
General overhead rough-in passed. Still need earthquake bracing installed and verified.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Troy Cobbley
|
|
|
Hanger attachments are ok for cover.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Troy Cobbley
|
|
|
Cover inspection for IBR Stub out passed. Piping/IBR can be covered.
Please call ROY, with time frame. Thanks and have a great day. Phone #: ###-#### Inspection requested via web by Jeff Packham
|