Permit Information
Permit NumberFIR18-00916
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 12251 W FRANKLIN RD
Project NameCJD Investments
Customer Number 
ePlanReviewYes
Description
New 36,532 Sq Ft 2 level Bldg to be fully sprinklered per NFPA13 & local codes, Occupancy Calss S-1 Construction Type II B, Point of connection to be Approx 50 ft from bldg after tee and valve by others. Under ground permit FIR18-00913
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/17/20196/17/20196/17/2019PPASS
DetailsTroy Cobbley
Permit finaled.

Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection6/15/20196/17/20196/17/2019ACANC
DetailsTroy Cobbley
Contractor was not ready for inspection when I was. Contact Andrew Larson ###-#### 30 min prior to Fire Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection6/13/20196/14/20196/14/2019PCANC
DetailsTroy Cobbley
To be rescheduled when the fire alarm contractor is ready.


Contact Andrew Larson ###-#### 30 min prior to Fire Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection6/6/20196/7/20196/7/2019PCANC
DetailsTroy Cobbley
Still need the underground supply line hydro passed and the valve added on the discharge side of the pump. Need devices tested with the Fire Alarm Control Panel.

Contact Andrew Larson ###-#### 30 min prior to fire final insp start please.

Thank you Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection6/5/20196/6/20196/6/2019PCANC
DetailsTroy Cobbley
not ready for final

Contact Andrew Larson ###-#### 30 min prior to Fire Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro6/4/20196/5/20196/5/2019APART
DetailsTroy Cobbley
Overhead hydro witnessed with no loss on the guage. The earthquake attachments have been addressed.
I discussed with Andrew the requirements for NFPA 20, A.4.15.6, 4.12.1.3, ball drip in the test header line and piping the relief valve

Contact Andrew Larson ###-#### 30 Min prior to Hydro Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro6/3/20196/4/20196/4/2019ANR
DetailsTroy Cobbley
Not ready for hydro test due to modifications needed. I noted that the below mezzanine piping is not controled separately as per Boise Fire Prevention Code Chapter 12; 5-12-51 "Floor Control". Also it appears a control valve on the discharge side of the fire pump "note 22" has not been installed. I need to contact plan review on other items listed in NFPA 20 that may need to be addressed.

Apparently the fire pump certification was performed without a Boise City Representative present as required per NFPA 20 14.2.2. I requested to be present several times to the onsite sprinkler fitter and the general contractor.

Contact Andrew Larson ###-#### 30 Min Prior to RTC insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro5/28/20195/29/20195/29/2019AFAIL
DetailsTroy Cobbley
**Head spacing around 2 unit heaters needs adjusted. Heads need to be added under overhead doors that roll back(3). Fire pump not ready for start-up**MAS**
Contact Andrew Larson ###-#### Fire Pump Start-Up Insp, plan to a lot plenty of time for the inspection.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro5/28/20195/28/20195/28/2019PCANC
DetailsTroy Cobbley
Contact Andrew Larson ###-#### - Fire Pump Start-Up - please allow plenty of time for the Inspection. Andrew Larson has stated that Troy Cobbley has requested to be in attendance for this Inspection which is scheduled with Nickerson Pumps at 1 PM 5/28 Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in5/20/20195/21/20195/21/2019APART
DetailsTroy Cobbley
Todays inspection was for the piping above the ceiling tile on the first floor. Piping can be covered except for where I need to verify the correct earth quake devices have been used.

Contact Andrew Larson ###-#### 30 min prior to RTC Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in5/9/20195/9/20195/9/2019PPART
DetailsTroy Cobbley
The sprinkler piping above the hardlids on the first floor, Entry Lobby/Restrooms, is ok for cover. See the city approved plans for locations as marked "ok". We also spoke about obstructions to the ESFR heads and the solid shelf racking possibly being a problem.
Contact Andrew Larson ###-#### 30 min prior to RTC Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in5/3/20195/6/20195/6/2019AFAIL
DetailsTroy Cobbley
Todays inspection was for the first floor hardlids. Piping can not be covered because the approved plans show 1 1/4" starters but 1" has been installed. Also no branchline restraints have been installed. There were no small documents or notes on site. I appears the trapeze bracing attachment rods are too small.


Contact Andrew Larson ###-#### 30 Min Prior to RTC Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank