INSP-Final Inspection | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Jim Page
|
|
|
Final inspection complete.
Phone #: ###-#### Inspection requested via web by Scott Carter II
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for basement level witnessed, no pressure loss observed.
Contact Noemi Carrero ###-#### 30 min prior to Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 7/1/2019 | 7/2/2019 | 7/2/2019 | P | PART |
Jim Page
|
|
|
Hydrostatic test for level 1 witnessed, no pressure loss observed.
Contact Noemi Carrero ###-#### 30 min Prior to OH Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | FAIL |
Jim Page
|
|
|
Basement level lost 4PSI during hydro, visible leak in corridor.
|
INSP-Sprinkler Rough-in | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in basement level complete, approved for cover, notated city approved drawings 3 areas that has exposed combustibles above ceiling grid, sprinkler protection will be required for mentioned areas, will verify coverage is in place during a follow up inspection. Level 1 sprinkler rough in complete.
Contact Ken Orahood ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PART |
Mark Stumbaugh
|
|
|
***OK to cover the pipe chase. Heads added on both side of the spiral duct as requested. Still waiting on heads to be installed in stairwell ceilings.**MAS**
Contact Ken Orahood ###-#### 30 min prior to RTC insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | FAIL |
Troy Cobbley
|
|
|
** Head needs to be added on other side of duct. If sheetrock doen't go all the way to the deck a head outside the chase on both sides of the duct would be acceptable.***MAS***
Contact Ken Orahood - ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | DONE |
Troy Cobbley
|
|
|
OK to cover hard ceilings only. Pipe chase needs to stay open. Need to add heads for 24" spiral duct. Area above ceiling in back stairwell needs to stay open till heads are installed. *MAS* Contact Ken Orahood - ###-#### 30 Min Prior to RTC insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
|