INSP-Final Inspection | 12/11/2019 | 12/12/2019 | 12/12/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, storage area that did not have fire sprinkler head located under the stairs was blocked off and not accessible at time of inspection. No sprinkler timer or irrigation solenoids have been installed at time of inspection and I could not confirm with the homeowner when the landscaping will be installed. Any and all irrigation that is part of the domestic water system (treated metered water) needs to isolate and shut off during water flow switch activation, as noted this was not installed at time of inspection and will be required when landscaping irrigation is installed. Final fire sprinkler inspection complete.
Please call Chris ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 12/9/2019 | 12/10/2019 | 12/10/2019 | P | FAIL |
Jim Page
|
|
|
Provide annual inspection for fire sprinkler backflow. Heads in apartment unit level 1 need heads raised so escutcheon covers entire hole. Add fire sprinkler in storage area under stairs on level 2 or make area under stairs not accessible.
Please call Jess before going out.
Thank you Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Jim Page
|
|
|
All tenting for overhead fire sprinkler piping in place at time of inspection, overhead fire sprinkler piping approved for cover. Noted that garage needs to be conditioned, garage needs to be maintained at 40 degrees or above to be code compliant.
Please call Clarence. This is an insulation inspection.
Thank you Phone #: ###-#### Inspection requested via web by Chris Gregory
|
INSP-Sprinkler Rough-in/Hydro | 3/15/2019 | 3/18/2019 | 3/18/2019 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, piping between conditioned spaces approved for cover, piping in attic spaces that requires tenting not approved for cover until tenting install is inspected and passed.
please call andre Phone #: ###-#### Inspection requested via web by Chris Gregory
|
INSP-Sprinkler Rough-in | 3/13/2019 | 3/15/2019 | 3/15/2019 | A | FAIL |
Jim Page
|
|
|
Tenting above pipe on the level 3 east end will not meet the minimum R38 requirements for tenting, piping will need to be lowered/adjusted to meet thr R38 requirements.