INSP-Final Inspection | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items for tenting have been corrected, all tenting in place at time of inspection, overhead fire sprinkler piping approved for cover.
Tenting Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | FAIL |
Jim Page
|
|
|
Piping exposed in north part of attic space. Tenting is not installed correctly in numerous areas at time of inspection, areas of concern will allow blow-in type insulation to get under pipe and filling pocket that is required between piping and sheetrock.
Tenting Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 5/17/2019 | 5/17/2019 | 5/17/2019 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, piping between conditioned spaces approved for cover, areas requiring tenting will be inspected at a later date, piping requiring tenting is not approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2019 | 5/17/2019 | 5/17/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Call James before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|