INSP-Final Inspection | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Please contact Tom Smalls for inspection time. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Final Inspection | 1/16/2020 | 1/17/2020 | 1/17/2020 | A | FAIL |
Troy Cobbley
|
|
|
For a final the test papers are needed and the canopies installed (need rock work) on the exterior dry sidewall sprinkler heads. Also the Life Safety Plan review Comments, note 35, state that Class 1 stand pipes are required. I have a call into plan review to verify an exception has been met.
Please contact Tom Smalls for a final inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | PASS |
Troy Cobbley
|
|
|
The forward flush passed. Please contact Rick Fry for time of inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 1/14/2020 | 1/15/2020 | 1/15/2020 | A | PASS |
Troy Cobbley
|
|
|
The remaining overhead hydro tests have been witnessed. This included the basement, stand pipe feed and the feed to the dry pipe system.
tOM Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 1/13/2020 | 1/14/2020 | 1/14/2020 | P | PASS |
Troy Cobbley
|
|
|
1st floor overhead piping hydro test witnessed with no pressure loss (North and South Buildings)
Please contact Tom Smalls for inspection time. This inspection is for 1st floor and parking garage. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | PASS |
Troy Cobbley
|
|
|
Hydro of the 2nd and 3rd floors passed.
Please Contact Tom Smalls for inspection time. The inspection is for hydro of the 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | PASS |
Troy Cobbley
|
|
|
**PASS* 1st floor common areas ok to cover. 1st floor units finaled for visual only.***MAS**
tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 | P | PASS |
Troy Cobbley
|
|
|
The second floor corridor rough-in passed and piping can be covered. The sprinkler work is complete/finaled in the third floor resident rooms.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PASS |
Troy Cobbley
|
|
|
**PASS Ok to cover 3rd floor common areas. MAS** 3rd floor tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for three additional rooms where piping has been ok'd to cover.
adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the first, second and third floor elevator lobby hard lids is ok for cover as marked on the plans.
Please contact Tom Smalls for inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2019 | 11/8/2019 | 11/8/2019 | A | PART |
Troy Cobbley
|
|
|
hydro dry system witnessed with no pressure loss. I looked at the elevator lobby for the 2nd and 3rd floors and discussed with Tom and Adam about adding a head in the soffit opposite of the elevators. // Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/25/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Troy Cobbley
|
|
|
Two more apartments on the first floor are ok for cover on the soffit piping. Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for parking garage piping complete.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for an additional apartment on the first floor south building where soffit piping is ok for cover. Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/17/2019 | 10/21/2019 | 10/21/2019 | A | FAIL |
Troy Cobbley
|
|
|
I left two messages for contact. Was at site but could not even park due to hyster. Do not have time to look site over for the contact. 1st floor - Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | CANC |
Troy Cobbley
|
|
|
WIll need to be rescheduled. Can not make it due to work load and personell shortage. 1st floor- Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | PASS |
Troy Cobbley
|
|
|
Two dry pendant heads for the trash shoot are ok for cover. Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Troy Cobbley
|
|
|
Piping in the soffits of an additional apartment is ok to cover as markedd on the plans. tOM- try to call but Tom will be in the parking garage and mignt noit have reception Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the apartment and the third floor corridor where piping is ok for cover.
tOM Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/26/2019 | 9/26/2019 | 9/26/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for three residences where the piping in the soffits is marked ok for cover. I also looked at the 2" piping in the connecting corridor for these rooms. tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/13/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Troy Cobbley
|
|
|
**Above ceiling area 3B ok to cover excluding corridor** MAS**
TOM IS WORKING IN THE PARKING GARAGE AND DOES NOT HAVE CELL SERVICE, PLEASE LOOK FOR HIM, THAKN YOU Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/9/2019 | 9/10/2019 | 9/10/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for first floor piping locations that are ok for cover. Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/26/2019 | 8/27/2019 | 8/27/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the other two north ground floor apartments where piping in the soffits is marked ok for cover.
tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PASS |
Troy Cobbley
|
|
|
See city plans for the two first floor north apartments where the sprinkler piping in the soffits is ok for cover. Tom Phone #: ###-####
|
INSP-Conference | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | DONE |
Troy Cobbley
|
|
|
Tom and I discussed obstructions in the mechanical closets. He is going to use one of the two exceptions allowed in NFPA 13R chapter 6. Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for level 2 complete for tenting and soffits, notated city approved drawings with yellow highlighter and red ink areas approved for cover.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/30/2019 | 7/31/2019 | 7/31/2019 | P | PART |
Troy Cobbley
|
|
|
**Unit V only on 2nd floor ok to cover. MAS**
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed for the south half of the third floor. Piping can be covered. Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | DONE |
Jim Page
|
|
|
24 hour air test for dry system on level 1 witnessed, no pressure loss observed.
|
INSP-Sprinkler Rough-in | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in level 1 apartment units and storage area complete, notated city approved drawings areas approved for cover, also notated sprinkler head in east corridor next to storage area that will require some type of freeze protection.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/26/2019 | 6/26/2019 | 6/26/2019 | A | PART |
Jim Page
|
|
|
Rough in inspection complete for levels 2 and 3 suites complete, notated city approved plans with pink highlighter areas that were inspected. Sprinkler piping in areas inspected that is betewwen conditioned spaces approved for cover, areas requiring tenting not approved for cover until tenting has been inspected and passed.
This an rough inspection for the 3rd and 2nd floor of the South side of the building. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping ok to cover in the third floor south building lobby. It has been clouded with todays date.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/17/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed for third floor north side apartment, all piping can be covered in this apartment. See city approved plans for notations.
tom Phone #: ###-####
|
INSP-Supply line flush | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush was witnessed.
Please contact Troy Nelson Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line hydro test witnessed.
Please call Troy Nelson Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Supply line flush | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Troy.
Please call Troy Nelson Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Troy Cobbley
|
|
|
The rough-in cover for 2nd floor North side passed as marked on the approved plans. Main corridor and lobby not complete yet.
. Please contact Tom Smalls. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PART |
Troy Cobbley
|
|
|
The existing underground supply piping is 4" instead of 6". Revised hydraulic calculations are required for the overhead system prior to a final sign off. The underground piping is ok for cover.
Please Contact Troy Nelson at ###-####, for time of inspection. This inspection is for underground rough -in. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 5/15/2019 | 5/15/2019 | 5/15/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for area marked on the north half of the third floor where tenting is approved and the sprinkler piping can be coverd.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Troy Cobbley
|
|
|
See the updated city approved plans for locations marked where piping is ok for cover on the first floor. Third floor was only a rough-in since not tenting has been done. The areas included the Suites on the first floor north half of the building and the Suites/Corridor/Lobby of the north half of the third floor.
|
INSP-Sprinkler Rough-in | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | FAIL |
Troy Cobbley
|
|
|
Plan mods are needed for the pipe routing changes and additional fittings. No cover given. Tom Phone #: ###-####
|