INSP-Final Inspection | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type scheduled.
Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro test was witnessed. Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed. 2,100 gallons of water flow verified with pitot guage.
Todd Ketterling is the contact. He would like this in the late AM. I''ve talked to Stacey with Suez and he is aware of this inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/8/2019 | 7/9/2019 | 7/9/2019 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover.
Bryan Collins is the contact for this underground RTC inspection. He is hoping for an early morning time slot. We appreciate your help with this. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for IBR and IBR thrust block complete, IBR approved for cover, remaining underground to be installed at a later date.
Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|