INSP-Final Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need as-builts prior to a final
|
INSP-Sprinkler Rough-in | 9/10/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler coverage has been adjusted in the corridors. Sprinkler piping is ok for cover. Call Paul Vaughn an hour before heading to the site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 9/5/2019 | 9/6/2019 | 9/6/2019 | P | PART |
Troy Cobbley
|
|
|
Only the individual rooms are ok for cover. The corridors can not be covered due to overspaced pendant heads.
Approved Plans are onsite with the contractor. Please call Paul Vaughn before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Final Inspection | 9/5/2019 | 9/6/2019 | 9/5/2019 | P | CANC |
Troy Cobbley
|
|
|
Approved Plans are onsite with the Contractor. Please Contact Paul Vaughn Before Heading to Job Site at Phone #: ###-#### >> Inspection requested via web by Matt Barnard Inspection cancelled from web by: Matt Barnard Inspection cancelled from web by: Matt Barnard
|
INSP-Sprinkler Rough-in | 6/12/2019 | 6/13/2019 | 6/13/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the remaining piping above the hardlids that is ok for cover.
Paul Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping that is above hardlids that is ok for cover.
Paul Vaugn is our Foreman onsite: ###-#### Phone #: ###-#### Inspection requested via web by Mick Woodburn
|