INSP-Final Inspection | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Per contractor the irrigation system is separate and does not require the automatic shut off valve.
Please call James before heading out! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | CANC |
Troy Cobbley
|
|
|
Cancel per James. Bell is not working. Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 9/9/2019 | 9/10/2019 | 9/10/2019 | P | CANC |
Troy Cobbley
|
|
|
Call James before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/1/2019 | 7/1/2019 | 7/1/2019 | A | PART |
Troy Cobbley
|
|
|
Tenting passed. Piping can be covered. Still need as-builts.
Call James if there are any issues. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 6/27/2019 | 6/27/2019 | 6/27/2019 | A | FAIL |
Jim Page
|
|
|
Sprinkler head in foyer is overspaced, head is more than 9 feet off of wall, spacing for this area is 16 X 16 so head needs to be a maximum of 8 feet off of wall. A wall has been added in the office, need to verify if the 20 X 20 spacing will work in this room with the new wall splitting the 2 heads shown on the city approved drawings. As-builts will be required for heads added for beam in entry hallway and changes to floor plan. No tenting installed at time of inspection.
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at 150PSI instead of the city static pressure, no pressure loss observed.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|