INSP-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Gabe Garduno is the field contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 10/18/2019 | 10/18/2019 | 10/18/2019 | A | PART |
Troy Cobbley
|
|
|
Fire sprinkler work complete in 105, 106, 205, 206, 305 and 306
|
INSP-Sprinkler Rough-in | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PART |
Troy Cobbley
|
|
|
The sprinkler work is complete in apartments 105, 106, 205, 206, 305 and 306.
|
INSP-Final Inspection | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PART |
Troy Cobbley
|
|
|
Fire sprinkler work complete in apartments 107, 108, 207, 208, 307 and 308.
Gabe Garduno is the contact. This final is for the first 12 units. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit number/building scheduled. Gabe Garduno is the contact for this final inspection. He is requesting an inspection for section 03 and 04. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/9/2019 | 9/10/2019 | 9/10/2019 | A | PASS |
Troy Cobbley
|
|
|
This is a duplicate inspection for approval to cover the two east most third floor apartments.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed for the top two apartments at the very east end of the building.
|
INSP-Sprinkler Rough-in/Hydro | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PASS |
Troy Cobbley
|
|
|
Hydro for the relo cated FDC witnesseed. Tenting repaired in the two third floor apartments on the east side of the center breezeway.. Gabe Garduno is the contact. This is for a FDC Hydro. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PART |
Troy Cobbley
|
|
|
Tenting on the third floor needs repaired. I noted two pendant heads that are overspaced on the third floor. First floor FDC piping has not been installed yet. No piping to be covered.
|
INSP-Sprinkler Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Troy Cobbley
|
|
|
Tenting is passed for the two west most 3rd floor apartments. Piping can be covered.
|
INSP-Sprinkler Rough-in | 8/6/2019 | 8/7/2019 | 8/7/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the 1st and 3rd floor piping in the west most apartments. @nd floor piping was previously approved. A tenting inspection will be required prior to a 3rd floor piping cover. 1st and 2nd floors are ok for cover on the west most apartments. Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 7/19/2019 | 7/22/2019 | 7/22/2019 | A | DONE |
Troy Cobbley
|
|
|
It appears the FDC will need to be relocated. I spoke to Cam and he is going to follow up and submitt a solution to Mark and myself.
Gabe Garduno is the contact for this consultation request . He wants to visit about the FDC Location. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | FAIL |
Jim Page
|
|
|
Numerous hangers/straps need to be added, need to add hangers where required, stopped inspection on level 1 after multiple apartments requiring additional straps.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2019 | 6/24/2019 | 6/24/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PART |
Troy Cobbley
|
|
|
Rough-in passed for the second floor, Piping can be covered except for the 1 1/2" drop downs at the BreezeWay since they have not been installed yet.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|