INSP-Final Inspection | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have benn corrected, final fire sprinkler inspection complete.
Backflow replaced with a double check valve as designed. Please call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 10/21/2019 | 10/22/2019 | 10/22/2019 | P | FAIL |
Jim Page
|
|
|
Backflow installed for fire sprinklers is a RPBA (reduce pressure backflow assembly), calculations for sprinkler system were designed with a double check, not and RP. System will need to be re-calculated for water flow demand or install double check as shown on city approved drawings.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 10/21/2019 | 10/21/2019 | 10/21/2019 | A | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints. Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 10/16/2019 | 10/16/2019 | 10/16/2019 | A | FAIL |
Troy Cobbley
|
|
|
***Failed - None of the items on the last inspection have been corrected. MAS***
Call James before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 9/17/2019 | 9/18/2019 | 9/18/2019 | P | FAIL |
Jim Page
|
|
|
Sprinkler escutcheon does not cover entire hole in 3 areas, master closet, master bedroom and sidewall under stairs. Sprinkler timer is sitting on garage floor, sprinkler timer must be in place and permanent wiring installed before final inspection.
Call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover approved for all overhead fire sprinkler piping.
Tenting Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 6/18/2019 | 6/19/2019 | 6/19/2019 | P | FAIL |
Jim Page
|
|
|
Tenting had not been started at time of inspection, request will need to be rescheduled.
Tenting Inspection, should be ready by afternoon. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, piping between conditioned spaces approved for cover, tenting inspection to be completed at a later date, areas requiring tenting not approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed at 150psi instead of static city pressure, no pressure loss observed.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|