INSP-Final Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Asbuilts approved, Troy said he would approve once as builts were approved. No inspection needed Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
INSP-Final Inspection | 8/26/2019 | 8/27/2019 | 8/27/2019 | A | CANC |
Troy Cobbley
|
|
|
Waiting for plan review approval of the as-builts. Brandon Phone #: ###-####Brandon Phone #: ###-####
|
INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Brandon Phone #: ###-####
|
INSP-Final Inspection | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | FAIL |
Jim Page
|
|
|
As discussed with Clint, Fire alarm install does not match city approved drawings, all sprinkler related devices are shown in the fire sprinkler riser room on level 1, tampers and flow for level 2 have been relocated to level 2, not on level 1 as shown on city approved drawings, instructed Clint on 09AUG2019 that city approved drawings need to be updated showing the change in order to complete inspections.
kristen Phone #: ###-####
|
INSP-Final Inspection | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with Clint at JCI, fire alarm inspection will be rescheduled to coincide with fire sprinkler inspection.
Damnian Phone #: ###-####
|