INSP-Final Inspection | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Rick Phone #: ###-####
|
INSP-Final Inspection | 9/20/2019 | 9/23/2019 | 9/23/2019 | A | CANC |
Troy Cobbley
|
|
|
The two fire alarm contractors did not schedule their inspections. Rick Phone #: ###-####
|
INSP-Final Inspection | 9/18/2019 | 9/19/2019 | 9/19/2019 | P | FAIL |
Troy Cobbley
|
|
|
T. I. work is not complete yet. Forward flush test passed. Also need the interconnections with the FACP tested. Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | PASS |
Troy Cobbley
|
|
|
**Hydro and rough-in passed. MAS**
r/i and OH hydro // Kerry ###-####
|
INSP-Supply line flush | 7/24/2019 | 7/24/2019 | 7/24/2019 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line hydro test was witnessed.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Troy Cobbley
|
|
|
The two thrust blocks are poured so the remaining piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Troy Cobbley
|
|
|
All underground supply piping is ok for cover except the two 90's which still need thrust blocks poured.. This inspection is for underground cover. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|