Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR19-00492
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 4184 S ORCHARD ST
Project NameTURBO AIR HANGER
Customer Number 
ePlanReviewYes
Description
**QUICK PERMIT** THIS IS A NEW GROUP II AIRCRAFT HANGER. TYPE II-B CONSTRUCTION. 29,423 sqft. ONE WET FIRE SPRINKLER SYSTEM TO BE INSTALLED. THIS PERMIT IS FOR THE DESIGNATED UNDERGROUND SPRINKLER LINE PORTION ONLY.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled3/10/20203/10/20203/10/2020PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection1/10/20201/13/20201/13/2020AFAIL
DetailsTroy Cobbley
Permit will need to be scheduled for a final when test papers have been emailed in as discussed.

Contact: George Jess, Final-AM. Thank you Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro11/22/201911/25/201911/25/2019APASS
DetailsTroy Cobbley
The underground hydro test witnessed. George Jess is the contact for this underground Hydro. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro11/21/201911/22/201911/22/2019AFAIL
DetailsTroy Cobbley
Went to job site first thing as discussed but found the guage on 0psi. I left a message on George's phone and sent picture of guage. George Jess is the contact for this underground Hydro. He is hoping for an appointment in the AM before Troy has to leave. Thanks so much. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush11/21/201911/21/201911/21/2019PPASS
DetailsTroy Cobbley
Underground flush witnessed.
INSP-Supply line flush11/18/201911/19/201911/19/2019ACANC
DetailsTroy Cobbley
George Jess will be the contact. Stacy Stuart has been contacted and will be on site at 930 AM so please meet him at this time. Thanks for all you do and I hope you have a great day! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in9/20/20199/23/20199/23/2019APASS
DetailsTroy Cobbley
The remaining underground supply piping is ok for cover. RTC inspection. We appreciate your help with this. Have a nice day. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in9/20/20199/20/20199/20/2019PPART
DetailsTroy Cobbley
The underground supply piping is ok to cover from the IBR to almost the point of connection. The piping at the point of connection is not complete yet.

Bryan is the contact. This is for an UG RTC. Please call him to confirm you can do the inspection this afternoon. Thank you so much for all of your help and I hope you have a great weekend!!

Thanks-
Alisha Phone #: ###-#### Inspection requested via web by Stan Beus