INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | PASS |
Mark Scharfen
|
|
|
Passed sprinkler final. All esctcheons installed and tiles in place. Stamped prints were on site.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/25/2019 | 7/25/2019 | 7/25/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.
Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|