INSP-Final Inspection | 1/28/2020 | 1/29/2020 | 1/29/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Plans on site Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 1/15/2020 | 1/17/2020 | 1/16/2020 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Final Inspection | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Final Inspection | 12/12/2019 | 12/13/2019 | 12/13/2019 | P | FAIL |
Troy Cobbley
|
|
|
Some ceiling tile is missing in nearly every room. Need all tile installed for a final. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 11/11/2019 | 11/12/2019 | 11/12/2019 | P | CANC |
Jim Page
|
|
|
Per conversation with installing contractor, this is a duplicate inspection request, this request is cancelled.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work is complete, approved for cover. City approved drawings points out a room that does not have a ceiling, no ceiling was installed at time of inspection. As stated on the city approved draiwngs if walls do not go all the way to the deck then that area will need to comply with 2016 NFPA 13 section 18.15.23.
If sprinkler heads are added due to the walls not going all the way to the deck then ceiling tiles will need to be removed to verify upright fire sprinkler addition to comply with NFPA 13.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Troy Cobbley
|
|
|
The two hard lids piping is ok for cover. . Phone #: ###-#### Inspection requested via web by Sam Ball
|