INSP-Final Inspection | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PASS |
Troy Cobbley
|
|
|
Previous corrections have been addressed. Piping is ok for cover. ]
Cover Inspection plumbing chase and wall issues. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 1/2/2020 | 1/7/2020 | 1/7/2020 | P | FAIL |
Troy Cobbley
|
|
|
Provide additional pendant at the main exit and in the combustible concealed space as discussed, insulation at the roof deck needs repaired.
Phone #: ###-#### Inspection requested via web by Connie Danes
|