INSP-Final Inspection | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Water meter changed per Suez. See the email attached in Documents for Boise Fire agreement on revised water flow.
Cam Phone #: ###-####
|
INSP-Final Inspection | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | FAIL |
Jim Page
|
|
|
Premit is under review as of these notes, final inspection cannot be performed until permit is back into issued status. According to SUEZ, water meter is a 5/8 water meter, not 1 inch as show on city approved documents.
Jon Beazer is the contact for this final inspection. Thank you for your help. Have a good day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 2/26/2020 | 2/27/2020 | 2/27/2020 | P | CANC |
Troy Cobbley
|
|
|
Cole Bierman is the contact for this final inspection. He is hoping for a PM appointment. He is needing an hour notice if possible as he will be working at another job site. Thank you for your help. Have a nice day. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | CANC |
Troy Cobbley
|
|
|
Cole Bierman is the contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | FAIL |
Troy Cobbley
|
|
|
Possible plan mods are needed due to the length of the actual underground supply, two houses fed off a single 1" supply and a 5/8" water meter. Repair the outside alarm bell and provide signage as discussed. Cole will be the contact. Please give him an hours notice to meet you there. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro witnessed with no pressure loss.
Cole will be the contact. Please give him an hours notice to meet you there. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Troy Cobbley
|
|
|
Tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | FAIL |
Troy Cobbley
|
|
|
Tenting needs repaired in the second floor bedroom and I need access to the area above the ceiling in the garage room.
|
INSP-Sprinkler Rough-in | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can not be covered until a tenting inspection has been passed. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|