INSP-Sprinkler Rough-in/Hydro | 2/10/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test was witnessed. Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover.
Kile Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line is ok for cover from the point of connection to the IBR. The IBR has not been installed yet and will require another inspection.
cover // Kyle Phone #: ###-####
|