INSP-Final Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | A | PASS |
Troy Cobbley
|
|
|
Forward flush passed. Permit finaled.
JON IS OUR FOREMAN ON SITE Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Final Inspection | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need to pass the forward flow test to get a final.
RICK FRY IS OUR CONTACT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 5/28/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Troy Cobbley
|
|
|
Hydro test for overhead witnessed. Please call Troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Supply line flush | 5/27/2020 | 5/27/2020 | 5/27/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush was witnessed. Please call Troy Nelson for time of inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 5/27/2020 | 5/27/2020 | 5/27/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro test was witnessed with no pressure loss.
Please call Troy Nelson for time of inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 3/30/2020 | 3/31/2020 | 3/31/2020 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping is ok for cover.
Rick Phone #: ###-####
|
INSP-Supply line flush | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply line piping is ok for cover.
TROY NELSON Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PART |
Troy Cobbley
|
|
|
**OK to cover hardlids only. NOT OK to plug head in wheelchair closet.. Branch line restraints need to be checked during full rough inspection. MAS**
Mike Phone #: ###-####
|