INSP-Supply line flush | 7/27/2020 | 7/29/2020 | 7/29/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground flush was witnessed.
The contact is Gabe Garduno Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/27/2020 | 7/29/2020 | 7/29/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro was witnessed. The contact is Gabe Garduno Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number scheduled.
Gabe Garduno is the contact. Thanks (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line issues have been addressed. Piping can be covered.
Kem Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | FAIL |
Troy Cobbley
|
|
|
It does not appear the bury depth meets 4'-6" for both the supply and breeze way piping as required by state and local code, the supply piping is utilizing mechanical restraints and the bolts are loose at the point of connection, the mechanical restraints have not been coated as per NFPA 13 10.6.2.5. No piping to be covered. ,
underground - Cam Phone #: ###-####
|