INSP-Final Inspection | 7/14/2020 | 7/15/2020 | 7/15/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work is complete.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 6/4/2020 | 6/4/2020 | 6/4/2020 | A | PASS |
Jim Page
|
|
|
Rough in inspection for remaining area of work is complete.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 4/13/2020 | 4/14/2020 | 4/14/2020 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping above hardlids in area of work is complete, city approved plans have been notated with red ink areas approved for cover.
Rough in for hard lids. Phone #: ###-#### Inspection requested via web by Sam Ball
|