Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberFIR20-00084
StatusFinaled
Name DELTA FIRE SYSTEMS
Site Address 2903 W TAFT ST
Project NameBrightstar Care Home
Customer Number 
ePlanReviewYes
Description
Install fire sprinkler per NFPA 13R 2016
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/10/20207/10/20207/10/2020APASS
DetailsGreg Ruxton
Fire sprinkler passed and finaled. Flow switch, tampers and PS in riser room tested. Interior and exterior sprinkler heads and escutchions inspected. Required signage, replacement heads and documentation in place in riser room.

Please Call Brian Flechs at ###-#### about 30 minutes prior to heading to job site. He will be coming from the office to meet you onsite and it will take him about 30 minutes to get there. Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Sprinkler Rough-in/Hydro4/27/20204/28/20204/28/2020PPASS
DetailsJim Page
All tenting in place at time of inspection, cover is approved, cover sticker has been placed.

This will be a rough in for approval to cover. Tenting is supposed to be installed today. Rick talked to Bill Garrett this morning and he said tenting will be complete. Please Rick before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Conference4/27/20204/27/20204/27/2020PDONE
DetailsJim Page
Fire conference with Bill for tenting requirements complete.

Tenting conference
INSP-Sprinkler Rough-in4/27/20204/27/20204/27/2020PCANC
DetailsJim Page
Inspection rescheduled for PM 28APR2020 per conversation with onsite GC Bill, this request turned into a conference, a fire conference has been generated, this request is cancelled.

This will be a rough in for approval to cover. Tenting is supposed to be installed today. Rick talked to Bill Garrett this morning and he said tenting will be complete. Please Rick before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Sprinkler Rough-in/Hydro4/21/20204/22/20204/22/2020ADONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping has been witnessed, no pressure loss observed at riser provided gauge.

Call Heath Day prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Sprinkler Rough-in4/21/20204/22/20204/22/2020APART
DetailsJim Page
Rough in inspection is complete, plans to be re-submitted to show minor modifications for minor changes made on-site. Tenting inspection to be completed at a later date, no tenting installed at time of this inspection, cover is not approved.

Call Heath Day prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Sprinkler Rough-in/Hydro4/21/20204/21/20204/21/2020PCANC
DetailsJim Page
Per conversation with point of contact, rough in and hydro rescheduled for 22APR2020, this request is cancelled.

Call Heath Day prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Supply line flush4/20/20204/21/20204/21/2020ADONE
DetailsJim Page
Supply line flush complete.

Please call Rick Fouts prior to heading to Job Site at ###-####. Rick will be Hermiston Oregon tomorrow, but if you can call Rick 30 - 45 minutes prior to arriving at job site he can get someone lined up to meet you out there. Phone #: ###-#### Inspection requested via web by Matt Barnard
INSP-Sprinkler Rough-in4/15/20204/15/20204/15/2020PPASS
DetailsJim Page
Rough to cover inspection for underground supply is complete, cover is approved.

*screened* Rick Phone #: ###-####