INSP-Final Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 | A | PASS |
Greg Ruxton
|
|
|
Fire sprinkler passed and finaled. Flow switch, tampers and PS in riser room tested. Interior and exterior sprinkler heads and escutchions inspected. Required signage, replacement heads and documentation in place in riser room.
Please Call Brian Flechs at ###-#### about 30 minutes prior to heading to job site. He will be coming from the office to meet you onsite and it will take him about 30 minutes to get there. Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in/Hydro | 4/27/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved, cover sticker has been placed.
This will be a rough in for approval to cover. Tenting is supposed to be installed today. Rick talked to Bill Garrett this morning and he said tenting will be complete. Please Rick before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Conference | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | DONE |
Jim Page
|
|
|
Fire conference with Bill for tenting requirements complete.
Tenting conference
|
INSP-Sprinkler Rough-in | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | CANC |
Jim Page
|
|
|
Inspection rescheduled for PM 28APR2020 per conversation with onsite GC Bill, this request turned into a conference, a fire conference has been generated, this request is cancelled.
This will be a rough in for approval to cover. Tenting is supposed to be installed today. Rick talked to Bill Garrett this morning and he said tenting will be complete. Please Rick before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in/Hydro | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping has been witnessed, no pressure loss observed at riser provided gauge.
Call Heath Day prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Jim Page
|
|
|
Rough in inspection is complete, plans to be re-submitted to show minor modifications for minor changes made on-site. Tenting inspection to be completed at a later date, no tenting installed at time of this inspection, cover is not approved.
Call Heath Day prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in/Hydro | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | CANC |
Jim Page
|
|
|
Per conversation with point of contact, rough in and hydro rescheduled for 22APR2020, this request is cancelled.
Call Heath Day prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Supply line flush | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | DONE |
Jim Page
|
|
|
Supply line flush complete.
Please call Rick Fouts prior to heading to Job Site at ###-####. Rick will be Hermiston Oregon tomorrow, but if you can call Rick 30 - 45 minutes prior to arriving at job site he can get someone lined up to meet you out there. Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply is complete, cover is approved.
*screened* Rick Phone #: ###-####
|