INSP-Final Inspection | 5/4/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, irrigation shutdown on flow switch activation has been witnessed.
Call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2020 | 5/4/2020 | 5/4/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler pipe witnessed at city pressure, no pressure loss observed at riser provided gauge.
Hydro before final, call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough passed, vertical pipe installed. Piping can be covered.
Call Anthony with any questions or concerns. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 2/13/2020 | 2/13/2020 | 2/13/2020 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping/tenting (all tenting in place at time of this inspection) is complete, all areas approved except for the area notated on the site city approved drawings where piping from level 1 to level 2 is not installed, piping needs installed and a follow up inspection will be required before cover.
for coverOverhead rough and tenting, call Anthony when heading out. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 2/13/2020 | 2/13/2020 | 2/13/2020 | P | CANC |
Troy Cobbley
|
|
|
Tenting inspection, call Anthony if there are any concerns Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|