INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Cover sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PART |
Jim Page
|
|
|
Previously noted item has been corrected, rough in inspection is complete. Tenting not installed at time of inspection, cover is not approved.
piping correction made Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | FAIL |
Jim Page
|
|
|
Notated city approved drawings that were onsite an area where the piping is in the attic space that requires tenting is to far away from heat source, relocate piping to wall cavity or provide heat calculations supporting area of install.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|