INSP-Sprinkler Rough-in/Hydro | 6/23/2020 | 6/25/2020 | 6/25/2020 | A | PASS |
Troy Cobbley
|
|
|
24hr air test and overhead 200lb test on dry system witnessed with no pressure loss.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in/Hydro | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PART |
Troy Cobbley
|
|
|
Overhead hydro for wet system witnessed. Dry system 24 hour air test started at 8:30 with 51psi on the guage. Plan mods are needed for the changes and inspection started over. Need through bolts for the EQ braces as discussed. Need insulation in the space above the riser room as discussed.
Leon is the contact. it is going to be 24hr air on dry and hydro on wet. Thank you sir Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Conference | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | DONE |
Troy Cobbley
|
|
|
Mike Martin and I talked about the need for the two dry pendants to be installed in the canopy. Thank you in advance Phone #: ###-#### Inspection requested via web by jeremiah robison
|