Permit Information
Permit NumberFIR20-00257
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 9605 S EISENMAN RD
Project NameBoise Gateway Building #1
Customer Number 
ePlanReviewYes
Description
Shilo will install 5 new ESFR systems in the new spec warehouse. These systems will be supplied by 1500 GPM @ 110 Fire Pump.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/1/20207/1/20207/1/2020PPASS
DetailsTroy Cobbley
Permit finaled.

Tony Cetani is the contact. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/30/20207/1/20207/1/2020AFAIL
DetailsTroy Cobbley
Need EQ bracing for fire pump assembly piping, need zone map, need clearance around underground stub in, need test papers.

Tony Cetani is the contact. This will be a fire alarm inspection. Thanks so much for all your help! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/30/20207/1/20206/30/2020ACANC
DetailsTroy Cobbley
Richard Clark is the contact. Have a great day! (: Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection6/29/20206/30/20206/30/2020PCANC
DetailsTroy Cobbley
Fire alarm was not ready.

Tony Cetani is the contact. This will be a fire alarm test. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/26/20206/29/20206/29/2020ACANC
DetailsTroy Cobbley
Cancel per Tony Cetani is the contact. This will be a final alarm test. Thank you!! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/23/20206/23/20206/23/2020PPART
DetailsJim Page
Partial final inspection is complete, will need to test all monitored devices in the fire pump room due too monitoring not being completely set up.

Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/22/20206/22/20206/22/2020PPASS
DetailsJim Page
Previously noted item has been corrected, rough in inspection complete.

Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/19/20206/19/20206/19/2020ADONE
DetailsJim Page
Fire pump commissioning complete.
INSP-Sprinkler Rough-in6/19/20206/19/20206/19/2020PFAIL
DetailsJim Page
Correct sway bracing as discussed.

Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus