INSP-Final Inspection | 4/5/2001 | 4/5/2001 | 4/5/2001 | P | PART |
Rick Jackson
|
|
|
###-#### hydro test of new standpipe in newly completed stairwell/main entrance okay 4/5/2001 1:19:07 PM
|
INSP-Final Inspection | 3/27/2001 | 3/28/2001 | 3/28/2001 | P | FAIL |
Rick Jackson
|
|
|
###-#### need to complete udner stair 3/28/2001 4:08:21 PM
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2000 | 3/13/2000 | 3/13/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 10:30:00. Contact: . Stand pipe and main riser hydro ok. 3/14/00 1:55:10 PM
|
INSP-Final Inspection | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | PART |
Rick Jackson
|
|
|
###-#### john 2nd floor hydro only, replace sprinkler heads with paint on d 3/14/00 10:46:18 AM deflectors. 3/14/00 10:46:35 AM
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2000 | 3/6/2000 | 3/6/2000 | P | PART |
Rick Jackson
|
|
|
###-#### pager Hydro complete on 4th floor. 3/7/00 8:50:26 AM
|
INSP-Sprinkler Rough-in/Hydro | 2/29/2000 | 2/29/2000 | 2/29/2000 | P | FAIL |
Rick Jackson
|
|
|
john pager ###-#### Flex couplings at riser; heads obstructed; C/N issued. 3/2/00 8:44:48 AM
|
INSP-Supply line flush | 1/24/2000 | 1/25/2000 | 1/25/2000 | P | PASS |
Rick Jackson
|
|
|
###-#### pager John Flush okay. 1/26/00 9:01:39 AM
|
INSP-Sprinkler Rough-in | 11/22/1999 | 11/23/1999 | 11/23/1999 | P | FAIL |
Rick Jackson
|
|
|
JOHN ###-#### 4th floor area only- heads not installed.
|