INSP-Final Inspection | 9/12/2001 | 9/12/2001 | 9/12/2001 | P | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 9/12/2001 4:26:56 PM
|
INSP-Final Inspection | 4/4/2000 | 4/5/2000 | 4/5/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/04/2000 at 17:49:37. Contact: ###-####. Final ok on sprkl. system addition. 4/6/00 8:50:00 AM
|
INSP-Alarm Testing | 2/24/2000 | 2/25/2000 | 2/25/2000 | A | PASS |
Joe Tawney
|
|
|
###-#### Ok on fire alarm system test. 2/25/00 3:12:59 PM
|
INSP-Final Inspection | 2/24/2000 | 2/25/2000 | 2/25/2000 | A | PASS |
Joe Tawney
|
|
|
###-#### or ###-#### Rob Ok on sprkl. 2/25/00 3:12:11 PM OK on sprkl. system for new hangar. 2/25/00 3:12:25 PM
|
INSP-Sprinkler Rough-in | 2/4/2000 | 2/4/2000 | 2/4/2000 | P | PART |
Rick Jackson
|
|
|
mick ###-#### Ok on hydro test & sprinkler R/I C/N issued on monitoring system. 2/7/00 8:56:22 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2000 | 2/3/2000 | 2/3/2000 | P | FAIL |
Joe Tawney
|
|
|
mick ###-#### Rescheduled not ready for inspection. 2/4/00 1:15:30 PM
|