GCB-Final | 1/28/2015 | 1/29/2015 | 1/30/2015 | P | PEND |
Dave Hannah
|
|
|
Mike ###-#### needs to resubmit new floor and elev plans showing changes.
|
GCB-Energy | 12/3/2012 | 12/4/2012 | 12/7/2012 | A | PASS |
Dave Hannah
|
|
|
Mike @ ###-####
|
GCB-Framing | 11/26/2012 | 11/26/2012 | 12/3/2012 | P | PASS |
Dave Hannah
|
|
|
Mike @ ###-####
|
GCB-Framing | 11/20/2012 | 11/21/2012 | 11/21/2012 | A | NH |
Tony Young
|
|
|
Mike @ ###-####,, no access,, called Mike 2 times,, no answer,, left 2 messeges
|
GCB-Courtesy | 11/5/2012 | 11/6/2012 | 11/6/2012 | A | DONE |
Dave Hannah
|
|
|
Mike @ ###-#### Call in advance
|
GCB-Footing | 2/5/2010 | 2/8/2010 | 2/8/2010 | A | PART |
Dave Hannah
|
|
|
Contact MIke @ ###-####Please call Mike prior to come in for inspection, ok to pour ftgs for int stairs note told contractos that he needs to resubmit plans he has made several changes also front wall is now cmu has no engineering or inspection
|
GCB-Footing | 9/16/2009 | 9/16/2009 | 9/17/2009 | P | PASS |
Dave Hannah
|
|
|
mike - please call 1/2 hr prior Phone #: ###-#### ok to pour stem wall ftg also ok
|
GCB-Footing | 9/1/2009 | 9/2/2009 | 9/2/2009 | A | FAIL |
Dave Hannah
|
|
|
mike - please call 1/2 hr prior to inspection Phone #: ###-#### ftg is ok but need property line surveyed so we can check setbacks
|