GCB-Final | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | PASS |
Mike Jordan
|
|
|
Trey @ ###-#### Call in advance to meet on site
|
GCB-Framing | 11/1/2012 | 11/1/2012 | 11/1/2012 | P | PASS |
Mike Jordan
|
|
|
Trey @ ###-####. Framing for deck and balcony as well as new roof over canopy ok.
|
GCB-Fndatn/slab ins/fld vent | 9/25/2012 | 9/26/2012 | 9/26/2012 | A | PASS |
Dave Hannah
|
|
|
Nathan @ ###-#### As close to 9 a.m. as possible
|
GCB-Footing | 9/20/2012 | 9/21/2012 | 9/21/2012 | A | PART |
Jim Sly
|
|
|
Nathan @ ###-#### AM inspection requested. Footings and reinforcement appear OK. Side setbacks appear OK. No plot plan on site.....un-able to verify rear setbacks. Talked to super...Trey and Gen. contractor Nathan about this. Also notified concrete contractor that if they pour, they are pouring at thier own risk.
|