GCB-Final | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Jim Sly
|
|
|
John ###-#### Unable to determine if all other permits are finaled. Structural final only........OK.
|
GCB-Energy | 2/6/2013 | 2/7/2013 | 2/7/2013 | A | PASS |
Jim Sly
|
|
|
John @ ###-####
|
GCB-Framing | 2/4/2013 | 2/5/2013 | 2/5/2013 | P | PASS |
Jim Sly
|
|
|
John @ ###-#### PM Inspection
|
GCB-Framing | 2/1/2013 | 2/4/2013 | 2/4/2013 | P | FAIL |
Mike Jordan
|
|
|
John @ ###-#### PM Inspection. Need mech. rough in inspection. Provide complete set of truss engineering. All portal frames to be nailed with 8d nails, no sub for staples on portal frame. Install the 2 potral frames in back, see approved plans.
|
GCB-Fndatn/slab ins/fld vent | 1/9/2013 | 1/10/2013 | 1/10/2013 | A | PASS |
Jim Sly
|
|
|
###-#### Note Very cold weather coming ......Advised concrete contractor to follow ACI 306 Cold weather guide to insure curing of concrete without freezing.
|
GCB-Footing | 1/8/2013 | 1/9/2013 | 1/9/2013 | P | PASS |
Jim Sly
|
|
|
Ryan @ ###-#### PM Inspection
|
GCB-Footing | 1/3/2013 | 1/4/2013 | 1/4/2013 | P | CANC |
Dave Hannah
|
|
|
Ryan @ ###-#### PM Inspection Inspection cancelled from web by: Barbara Stitt
|