GCB-Final | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Dave Hannah
|
|
|
Heather Dennis ###-#### - egress doors
|
FIRE-Final Inspection | 4/8/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Scott Arellano
|
|
|
Passed.
|
FIRE-Final Inspection | 3/17/2015 | 3/23/2015 | 3/23/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide Fire Alarm Permit for the interconnection of the new access control egress doors and the fire alarm panel. I tested the sensor, button and release on alarm already.
|
GCB-Final | 1/21/2015 | 1/22/2015 | 1/22/2015 | A | FAIL |
Mike Jordan
|
|
|
###-#### - need final on egress doors. Push to exit button not located within 5ft. of door, needs fire final as well.
|
GCB-Final | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | PASS |
Jim Sly
|
|
|
Gary Gettman ###-#### please call 30 min prior to meet onsite
|
FIRE-Final Inspection | 8/26/2014 | 8/26/2014 | 8/26/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
GCB-Final | 8/21/2014 | 8/22/2014 | 8/22/2014 | A | FAIL |
Dave Hannah
|
|
|
gary ###-#### sinks are to high no fire inspect?ion no mec inspection ect
|
GCB-Framing | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Mike Jordan
|
|
|
|