GCB-Final | 11/4/2015 | 11/6/2015 | 11/6/2015 | A | PASS |
Jim Sly
|
|
|
Roger ###-#### - final for entire project OK for perm. occ.
|
FIRE-Final Inspection | 11/2/2015 | 11/3/2015 | 11/4/2015 | A | PASS |
Katie Marron
|
|
|
Fire Life Safety Pass.
Riser room signage, map at annuciator with FACP and riser call outs and device map at FACP verified
|
GCB-Final | 10/28/2015 | 10/30/2015 | 10/30/2015 | P | PART |
Jim Sly
|
|
|
Roger 435.764.3479 - Temp occ. for units 114, 215, 216, 217, 313, 314, and 315.
|
FIRE-Final Inspection | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | PART |
Thomas Walsh
|
|
|
Fire life-safety inspection for the south wing, including exit signage and emergency lighting test. All tested OK. Conducted partial fire alarm testing in this wing, however fire sprinkler flow testing could not be performed. Fire door hardware installation (unit doors, stairwell doors and fire cross corridor fire doors) is still a works in progress and would need to be completed prior to TCO of this wing. NOTE: The existing TCO area should include up to units 114, 215-217 and 313-315.
|
FIRE-Conference | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | DONE |
Thomas Walsh
|
|
|
Called to discuss inspections needed today.
|
GCB-Final | 10/23/2015 | 10/23/2015 | 10/23/2015 | A | PEND |
Jim Sly
|
|
|
final for 7 units-Roger ###-#### Waiting to verify that Fire ........and all trades are OK with Temp. on theses units.
|
GCB-Final | 9/30/2015 | 9/30/2015 | 10/1/2015 | P | PART |
Jim Sly
|
|
|
Roger ###-#### - units: 110-120, 215-223, 313-321 - partial final for temp c of o Partial ......Temp Occ. for Units 110-120 215-233 and 313-321 . OK for Temp Occ. for these units on 9/30/15 .
|
FIRE-Final Inspection | 10/1/2015 | 10/2/2015 | 10/1/2015 | A | PART |
Katie Marron
|
|
|
Fire Life Safety complete for North East section. Ok for temporary occupancy.
|
FIRE-Hydro test above ground | 10/1/2015 | 10/2/2015 | 10/1/2015 | A | CANC |
Dave Hannah
|
|
|
Phone #: 4357643479 >> Inspection requested via mobile web by Roger Titmus Inspection cancelled via mobile web on Thursday, October 01, 2015.
|
FIRE-Hydro test above ground | 9/30/2015 | 10/1/2015 | 10/1/2015 | A | DEFR |
Dave Hannah
|
|
|
Call prior to going Phone #: 4357643479 >> Inspection requested via mobile web by Roger Titmus sent to firew
|
GCB-Courtesy | 9/23/2015 | 9/23/2015 | 9/23/2015 | P | DONE |
Jim Sly
|
|
|
Roger ###-#### - requested consultation w/Jim Sly
|
GCB-Ceiling Grid | 9/2/2015 | 9/2/2015 | 9/2/2015 | P | PASS |
Phil Shearer
|
|
|
Gary ###-#### - 1st - 3rd Floors E. Wing
|
GCB-Ceiling Grid | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | FAIL |
Phil Shearer
|
|
|
Gary ###-#### - 1st-3rd floors E. wing. Penetrations in fire walls.
|
GCB-Energy | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Sly
|
|
|
Gary ###-#### - S. wing 3rd floor
|
GCB-Framing | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | PASS |
Jim Sly
|
|
|
Gary ###-#### - 3rd floor S. wing
|
GCB-Energy | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### - 2nd Floor......Wing parrallel with 42nd St. OK.
|
GCB-Framing | 8/11/2015 | 8/11/2015 | 8/11/2015 | P | CANC |
Jim Sly
|
|
|
Gary ###-#### - 3rd floor S. wing
|
GCB-Framing | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Jim Sly
|
|
|
Gary ###-#### - 3rd floor
|
GCB-Energy | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Jim Sly
|
|
|
Gary ###-#### - 2nd floor & 1st - 3rd floor common areas
|
GCB-Framing | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Jim Sly
|
|
|
Gary ###-#### - 2nd & 3rd floor common areas
|
GCB-Framing | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PART |
Jim Sly
|
|
|
Gary ###-#### - 2nd floor S. Wing Units 202 thru 211. Just need a few more firestops.....will check at Energy.
|
GCB-Energy | 7/30/2015 | 7/30/2015 | 7/30/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### All rooms 1st floor noted on previous inspection.
|
GCB-Framing | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | PART |
Jim Sly
|
|
|
Gary ###-#### Rooms 105 thru 113 main floor .....OK.
|
GCB-Framing | 7/20/2015 | 7/20/2015 | 7/20/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### common area 1st floor ok
|
GCB-Framing | 7/15/2015 | 7/15/2015 | 7/15/2015 | P | PEND |
Jim Sly
|
|
|
Gary ###-#### Walk thru with Gary........Misc Firecaulking to be completed.
|
GCB-Energy | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Jim Sly
|
|
|
Gary ###-#### all three floors........rooms only ....located between the 2hr walls.
|
GCB-Framing | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Phil Shearer
|
|
|
Gary ###-#### - 1st-3rd floor All rooms ok to insulate between 2 hour walls.
|
GCB-Framing | 6/18/2015 | 6/18/2015 | 6/18/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### - area 1st floor..........Middle of bldg....between 2 hr walls ..........OK to insulate Ext. walls in units....only.
|
GCB-Courtesy | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | CANC |
Jim Sly
|
|
|
Gary ###-#### - requested inspection ......Canc by contr....
|
GCB-Energy | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PART |
Phil Shearer
|
|
|
Gary ###-#### - equipment maintenance room OK for cover
|
GCB-Energy | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | CANC |
Jim Sly
|
|
|
Gary ###-####
|
GCB-Energy | 6/5/2015 | 6/8/2015 | 6/8/2015 | A | PASS |
Phil Shearer
|
|
|
Gary ###-####. 3rd flr South of 2 hr wall
|
FIRE-Sprinkler Rough-in | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | DONE |
Katie Marron
|
|
|
Completed 6/4/15 for sprinkler permit.
|
GCB-Courtesy | 6/2/2015 | 6/2/2015 | 6/3/2015 | P | DONE |
Jim Sly
|
|
|
Gary ###-#### - conference for cover 3rd floor Pending sprinkler tenting insp. 3rd flr South of 2 hr wall.
|
GCB-Courtesy | 5/29/2015 | 6/1/2015 | 6/1/2015 | A | DONE |
Jim Sly
|
|
|
Gary ###-#### - energy conference ........
|
GCB-Framing | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### 3rd floor East wing from 2hr wall to theSouth OK except draftstops.
|
FIRE-Conference | 5/20/2015 | 5/20/2015 | 5/26/2015 | P | DONE |
Katie Marron
|
|
|
Completed 5/21
|
GCB-Energy | 5/20/2015 | 5/21/2015 | 5/21/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### OK to cover 1st and 2nd floors ........East wing ......South of 2hr wall.
|
FIRE-Conference | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | DONE |
Troy Cobbley
|
|
|
Gary, myself, the electrician and the fire sprinkler contractor discussed obstructions to the fire sprinkler pendants and the required separation distances.
|
GCB-Energy | 5/19/2015 | 5/19/2015 | 5/19/2015 | P | NR |
Jim Sly
|
|
|
Gary ###-####
|
GCB-Framing | 5/8/2015 | 5/11/2015 | 5/11/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### OK to insulate exterior walls and select interior walls........1st and 2nd floors.
|
GCB-Framing | 5/7/2015 | 5/8/2015 | 5/8/2015 | A | PEND |
Jim Sly
|
|
|
Gary ###-#### - E. Wing - Levels 1, 2, 3 Walk thru.........pointed out some corrections.
|
FIRE-Conference | 5/6/2015 | 5/7/2015 | 5/7/2015 | A | DONE |
Katie Marron
|
|
|
Walkthough with PM and General Contractor. Discussed requirements for possible temporary occupancy (full shell and core protection, system monitoring, fire department access, and adequate egress/exit access). Discussed that original idea to first fire wall would not satisfy exit access, so common area would need to be complete as well.
|
GCB-Framing | 5/5/2015 | 5/5/2015 | 5/5/2015 | P | PASS |
Jim Sly
|
|
|
Gary ###-#### - roof nailing insp.
|
GCB-Courtesy | 5/1/2015 | 5/4/2015 | 5/4/2015 | A | DONE |
Jim Sly
|
|
|
Gary ###-#### - discuss framing
|
GCB-Courtesy | 4/21/2015 | 4/21/2015 | 4/21/2015 | P | DONE |
Jim Sly
|
|
|
Gary ###-#### Walk thru.....firestopping
|
GCB-Framing | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | PART |
Jim Sly
|
|
|
Gary ###-#### - shearnail insp. on S. Wing........OK
|
GCB-Courtesy | 4/6/2015 | 4/7/2015 | 4/7/2015 | A | DONE |
Jim Sly
|
|
|
Gary ###-#### C/N Floor/Ceiling assembly L528 at room area shows Gypcrete as part of the assembly. If gypcrete not installed beneath tubs, Provide alternate to Garden City/ Boise City for approval.
|
GCB-Courtesy | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | DONE |
Jim Sly
|
|
|
Gary ###-####
|
GCB-Framing | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | PART |
Jim Sly
|
|
|
Gary ###-#### Preliminary inspection of sheetrock on 2hr walls. OK to insulate select walls not containing any Plumb, Electr, or Mech. Nailing around windows OK Ok to install window wrap.
|
GCB-Courtesy | 3/31/2015 | 3/31/2015 | 3/31/2015 | P | DONE |
Phil Shearer
|
|
|
Gary ###-####
|
GCB-Framing | 3/30/2015 | 3/30/2015 | 3/30/2015 | P | PART |
Jim Sly
|
|
|
Gary ###-#### - roof nail insp. W. 1/2 of N. wing. OK
|
GCB-Framing | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | PASS |
Phil Shearer
|
|
|
Gary ###-#### - roof nail insp.Roof nailing on North 2/3 of South wing ....OK
|
GCB-Shearwall | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PART |
Jim Sly
|
|
|
Gary ###-#### - shearnail and roof nail insp. requested Exterior Shear nailing OK at East Wing 3 Floors.
|
GCB-Courtesy | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | DONE |
Phil Shearer
|
|
|
Gary ###-#### or ###-####.Waiting on aprovel to us metal in drop celing in place of the 2x4s
|
GCB-Courtesy | 3/11/2015 | 3/12/2015 | 3/12/2015 | A | DONE |
Jim Sly
|
|
|
Gary ###-#### - conference requested w/Jim Sly Corr Notice......Maintain 2 ;layers each side 2 hr walls 5/8 type x gyp. without wood penitrations per approved plan.
|
GCB-Framing | 3/10/2015 | 3/11/2015 | 3/11/2015 | A | PART |
Phil Shearer
|
|
|
Gary ###-#### - roofing insp. Roof Insp. Roof nailing on north 1/3 of East wing ....OK
|
GCB-Framing | 3/6/2015 | 3/9/2015 | 3/10/2015 | A | PART |
Jim Sly
|
|
|
Roger ###-#### - Roof Insp. Roof nailing on South 2/3 of East wing ....OK
|
GCB-Courtesy | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | DONE |
Jim Sly
|
|
|
Larry phone ###-#### Meeting with Plumber.....about Firestopping.
|
GCB-Courtesy | 2/24/2015 | 2/25/2015 | 2/25/2015 | P | DONE |
Jim Sly
|
|
|
Larry ###-#### - requested 2p.m. Would like to discuss mechanical as well Pre-Construction Conference Met with Dixie Fellows and Mech. contractor. Met with Structural inspectors....Dave Hannah, Phil Shearer, Tony Young. Brought Sam Zahorka plan check for ride along. Architects were also present.
|
GCB-Fndatn/slab ins/fld vent | 11/25/2014 | 11/26/2014 | 11/28/2014 | P | PASS |
Dave Hannah
|
|
|
Pete ###-#### - slab/interior footings
|
GCB-Energy | 11/25/2014 | 11/26/2014 | 11/26/2014 | A | PART |
Dave Hannah
|
|
|
Larry ###-#### - energy compliance: slab on grade for foam north
|
GCB-Fndatn/slab ins/fld vent | 11/24/2014 | 11/25/2014 | 11/25/2014 | A | PASS |
Dave Hannah
|
|
|
Alvaro ###-#### - requested 9am inspection
|
GCB-Footing | 11/18/2014 | 11/19/2014 | 11/20/2014 | P | PART |
Dave Hannah
|
|
|
Alvaro ###-#### - requested appt. at 2p.m.
|
GCB-Fndatn/slab ins/fld vent | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PEND |
Dave Hannah
|
|
|
Alvaro ###-#### - requested 2p.m. appt. to cold to place concrete with outub heat
|
GCB-Footing | 11/10/2014 | 11/10/2014 | 11/12/2014 | P | PEND |
Dave Hannah
|
|
|
Alvaro ###-#### spec inspection wii do final sign off of rebar
|
GCB-Footing | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | CANC |
Phil Shearer
|
|
|
Alvaro ###-####
|
GCB-Stem wall | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | PART |
Phil Shearer
|
|
|
Alvaro ###-####
|
GCB-Footing | 11/3/2014 | 11/3/2014 | 11/4/2014 | P | PART |
Dave Hannah
|
|
|
Alvaro ###-#### - requested insp. at 2p.m. crew is woking on rebar mti will be on site for spec inspection
|