Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberGCB14-00099
StatusFinaled
Name HUTCHISON SMITH ARCHITECTS
Site Address 415 E 42ND ST
Project NameBLD2014-00099
Customer Number 
ePlanReviewNo
Description
(Trailwinds Apartments) - **3/6/15 PLAN MODIFICATION TO INCLUDE: FURNISH INSTALL IDAHO POWER CONDUCTORS AND A RISER DIAGRAM FEEDER CLARIFICATION; APPROVAL OF MEMBRANE PENETRATION DETAILS. SRZ**1/27/15 PLAN MODIFICATION TO INCLUDE: REVISE THE RETURN AIR DUCTING AT FITNESS ROOM 184; REVISE LIGHT FIXTURES IN MID CORRIDOR; AND REVISE ELECTRICAL RECEPTACLE LAYOUTS IN UNIT KITCHENS. SRZ** - 12/3/14 PLAN MODIFICATION TO INCLUDE: RELOCATE WATER HEATERS & FCU'S IN SEPARATE CLOSETS; RE-ROUTE HVAC DUCTS & DAMPERS SERVING THE 2ND & 3RD FLOORS MID CORRIDOR & EAST CORRIDOR; MIRRORED JANITOR ROOM #187 TO COMBINE WATER HEATERS FOR JANITOR SINK AND COFFEE COUNTER. SRZ** 10/31/14 PLAN MODIFICATION TO INCLUDE: CHANGE THE GRADE BEAM FOUNDATION DESIGN TO A TRADITIONAL SPREAD FOOTING AND FOUNDATION WALL PER ENGINEERED DRAWINGS. SRZ** To construct a new woof frame, Three story, 73,635 square foot, 64 unit, Multi-Family Dwelling apartment building per the approved plans. Two Fire walls separate this building into three separate buildings for building area compliance. Building 'A' has a total of 11,036 square feet. Building 'B' has a total of 7,094 square feet. Building 'C' has a total of 6,613 square feet. One hour fire-partitions and horizontal separations are required between dwelling units. All dwelling units are required to comply as Type B units. Five Type B units are also provided. Work includes: associated site work, footing & foundation, structural & non-structural framing; electrical, mechanical, plumbing, sprinkler & alarm work. All construction per the approved plans, attached plan review report, and applicable adopted codes. NOTE: This building is required to be fire sprinklered for occupancy and area increase requirements. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final11/4/201511/6/201511/6/2015APASS
DetailsJim Sly
Roger ###-#### - final for entire project
OK for perm. occ.
FIRE-Final Inspection11/2/201511/3/201511/4/2015APASS
DetailsKatie Marron
Fire Life Safety Pass.

Riser room signage, map at annuciator with FACP and riser call outs and device map at FACP verified
GCB-Final10/28/201510/30/201510/30/2015PPART
DetailsJim Sly
Roger 435.764.3479 - Temp occ. for units 114, 215, 216, 217, 313, 314, and 315.
FIRE-Final Inspection10/29/201510/30/201510/30/2015APART
DetailsThomas Walsh
Fire life-safety inspection for the south wing, including exit signage and emergency lighting test. All tested OK. Conducted partial fire alarm testing in this wing, however fire sprinkler flow testing could not be performed. Fire door hardware installation (unit doors, stairwell doors and fire cross corridor fire doors) is still a works in progress and would need to be completed prior to TCO of this wing.
NOTE: The existing TCO area should include up to units 114, 215-217 and 313-315.
FIRE-Conference10/29/201510/30/201510/30/2015ADONE
DetailsThomas Walsh
Called to discuss inspections needed today.
GCB-Final10/23/201510/23/201510/23/2015APEND
DetailsJim Sly
final for 7 units-Roger ###-####
Waiting to verify that Fire ........and all trades are OK with Temp. on theses units.
GCB-Final9/30/20159/30/201510/1/2015PPART
DetailsJim Sly
Roger ###-#### - units: 110-120, 215-223, 313-321 - partial final for temp c of o
Partial ......Temp Occ. for Units 110-120 215-233 and 313-321 . OK for Temp Occ. for these units on 9/30/15 .
FIRE-Final Inspection10/1/201510/2/201510/1/2015APART
DetailsKatie Marron
Fire Life Safety complete for North East section. Ok for temporary occupancy.
FIRE-Hydro test above ground10/1/201510/2/201510/1/2015ACANC
DetailsDave Hannah
Phone #: 4357643479 >> Inspection requested via mobile web by Roger Titmus Inspection cancelled via mobile web on Thursday, October 01, 2015.
FIRE-Hydro test above ground9/30/201510/1/201510/1/2015ADEFR
DetailsDave Hannah
Call prior to going Phone #: 4357643479 >> Inspection requested via mobile web by Roger Titmus sent to firew
GCB-Courtesy9/23/20159/23/20159/23/2015PDONE
DetailsJim Sly
Roger ###-#### - requested consultation w/Jim Sly
GCB-Ceiling Grid9/2/20159/2/20159/2/2015PPASS
DetailsPhil Shearer
Gary ###-#### - 1st - 3rd Floors E. Wing
GCB-Ceiling Grid9/1/20159/2/20159/2/2015AFAIL
DetailsPhil Shearer
Gary ###-#### - 1st-3rd floors E. wing. Penetrations in fire walls.
GCB-Energy8/20/20158/21/20158/21/2015APASS
DetailsJim Sly
Gary ###-#### - S. wing 3rd floor
GCB-Framing8/13/20158/13/20158/13/2015PPASS
DetailsJim Sly
Gary ###-#### - 3rd floor S. wing
GCB-Energy8/13/20158/13/20158/13/2015PPART
DetailsJim Sly
Gary ###-#### - 2nd Floor......Wing parrallel with 42nd St. OK.
GCB-Framing8/11/20158/11/20158/11/2015PCANC
DetailsJim Sly
Gary ###-#### - 3rd floor S. wing
GCB-Framing8/6/20158/7/20158/7/2015APASS
DetailsJim Sly
Gary ###-#### - 3rd floor
GCB-Energy8/6/20158/7/20158/7/2015APASS
DetailsJim Sly
Gary ###-#### - 2nd floor & 1st - 3rd floor common areas
GCB-Framing8/6/20158/6/20158/6/2015PPASS
DetailsJim Sly
Gary ###-#### - 2nd & 3rd floor common areas
GCB-Framing8/4/20158/5/20158/5/2015APART
DetailsJim Sly
Gary ###-#### - 2nd floor S. Wing
Units 202 thru 211. Just need a few more firestops.....will check at Energy.
GCB-Energy7/30/20157/30/20157/30/2015PPART
DetailsJim Sly
Gary ###-####
All rooms 1st floor noted on previous inspection.
GCB-Framing7/22/20157/23/20157/23/2015APART
DetailsJim Sly
Gary ###-####
Rooms 105 thru 113 main floor .....OK.
GCB-Framing7/20/20157/20/20157/20/2015PPART
DetailsJim Sly
Gary ###-####
common area 1st floor ok
GCB-Framing7/15/20157/15/20157/15/2015PPEND
DetailsJim Sly
Gary ###-####
Walk thru with Gary........Misc Firecaulking to be completed.
GCB-Energy7/6/20157/7/20157/7/2015APASS
DetailsJim Sly
Gary ###-####
all three floors........rooms only ....located between the 2hr walls.
GCB-Framing6/30/20156/30/20156/30/2015PPASS
DetailsPhil Shearer
Gary ###-#### - 1st-3rd floor All rooms ok to insulate between 2 hour walls.
GCB-Framing6/18/20156/18/20156/18/2015PPART
DetailsJim Sly
Gary ###-#### - area 1st floor..........Middle of bldg....between 2 hr walls ..........OK to insulate Ext. walls in units....only.
GCB-Courtesy6/15/20156/16/20156/16/2015ACANC
DetailsJim Sly
Gary ###-#### - requested inspection ......Canc by contr....
GCB-Energy6/11/20156/12/20156/12/2015APART
DetailsPhil Shearer
Gary ###-#### - equipment maintenance room OK for cover
GCB-Energy6/9/20156/10/20156/10/2015ACANC
DetailsJim Sly
Gary ###-####
GCB-Energy6/5/20156/8/20156/8/2015APASS
DetailsPhil Shearer
Gary ###-####. 3rd flr South of 2 hr wall
FIRE-Sprinkler Rough-in6/4/20156/5/20156/5/2015ADONE
DetailsKatie Marron
Completed 6/4/15 for sprinkler permit.
GCB-Courtesy6/2/20156/2/20156/3/2015PDONE
DetailsJim Sly
Gary ###-#### - conference for cover
3rd floor Pending sprinkler tenting insp. 3rd flr South of 2 hr wall.
GCB-Courtesy5/29/20156/1/20156/1/2015ADONE
DetailsJim Sly
Gary ###-#### - energy conference ........
GCB-Framing5/28/20155/28/20155/28/2015PPART
DetailsJim Sly
Gary ###-####
3rd floor East wing from 2hr wall to theSouth OK except draftstops.
FIRE-Conference5/20/20155/20/20155/26/2015PDONE
DetailsKatie Marron
Completed 5/21
GCB-Energy5/20/20155/21/20155/21/2015PPART
DetailsJim Sly
Gary ###-####
OK to cover 1st and 2nd floors ........East wing ......South of 2hr wall.
FIRE-Conference5/20/20155/21/20155/21/2015ADONE
DetailsTroy Cobbley
Gary, myself, the electrician and the fire sprinkler contractor discussed obstructions to the fire sprinkler pendants and the required separation distances.
GCB-Energy5/19/20155/19/20155/19/2015PNR
DetailsJim Sly
Gary ###-####
GCB-Framing5/8/20155/11/20155/11/2015PPART
DetailsJim Sly
Gary ###-####
OK to insulate exterior walls and select interior walls........1st and 2nd floors.
GCB-Framing5/7/20155/8/20155/8/2015APEND
DetailsJim Sly
Gary ###-#### - E. Wing - Levels 1, 2, 3
Walk thru.........pointed out some corrections.
FIRE-Conference5/6/20155/7/20155/7/2015ADONE
DetailsKatie Marron
Walkthough with PM and General Contractor. Discussed requirements for possible temporary occupancy (full shell and core protection, system monitoring, fire department access, and adequate egress/exit access). Discussed that original idea to first fire wall would not satisfy exit access, so common area would need to be complete as well.
GCB-Framing5/5/20155/5/20155/5/2015PPASS
DetailsJim Sly
Gary ###-#### - roof nailing insp.
GCB-Courtesy5/1/20155/4/20155/4/2015ADONE
DetailsJim Sly
Gary ###-#### - discuss framing
GCB-Courtesy4/21/20154/21/20154/21/2015PDONE
DetailsJim Sly
Gary ###-####
Walk thru.....firestopping
GCB-Framing4/8/20154/9/20154/9/2015APART
DetailsJim Sly
Gary ###-#### - shearnail insp. on S. Wing........OK
GCB-Courtesy4/6/20154/7/20154/7/2015ADONE
DetailsJim Sly
Gary ###-####
C/N Floor/Ceiling assembly L528 at room area shows Gypcrete as part of the assembly. If gypcrete not installed beneath tubs, Provide alternate to Garden City/ Boise City for approval.
GCB-Courtesy4/2/20154/3/20154/3/2015ADONE
DetailsJim Sly
Gary ###-####
GCB-Framing4/2/20154/3/20154/3/2015APART
DetailsJim Sly
Gary ###-####
Preliminary inspection of sheetrock on 2hr walls. OK to insulate select walls not containing any Plumb, Electr, or Mech. Nailing around windows OK Ok to install window wrap.
GCB-Courtesy3/31/20153/31/20153/31/2015PDONE
DetailsPhil Shearer
Gary ###-####
GCB-Framing3/30/20153/30/20153/30/2015PPART
DetailsJim Sly
Gary ###-#### - roof nail insp.
W. 1/2 of N. wing. OK
GCB-Framing3/26/20153/27/20153/27/2015APASS
DetailsPhil Shearer
Gary ###-#### - roof nail insp.Roof nailing on North 2/3 of South wing ....OK
GCB-Shearwall3/24/20153/25/20153/25/2015APART
DetailsJim Sly
Gary ###-#### - shearnail and roof nail insp. requested
Exterior Shear nailing OK at East Wing 3 Floors.
GCB-Courtesy3/19/20153/19/20153/19/2015PDONE
DetailsPhil Shearer
Gary ###-#### or ###-####.Waiting on aprovel to us metal in drop celing in place of the 2x4s
GCB-Courtesy3/11/20153/12/20153/12/2015ADONE
DetailsJim Sly
Gary ###-#### - conference requested w/Jim Sly
Corr Notice......Maintain 2 ;layers each side 2 hr walls 5/8 type x gyp. without wood penitrations per approved plan.
GCB-Framing3/10/20153/11/20153/11/2015APART
DetailsPhil Shearer
Gary ###-#### - roofing insp. Roof Insp.
Roof nailing on north 1/3 of East wing ....OK
GCB-Framing3/6/20153/9/20153/10/2015APART
DetailsJim Sly
Roger ###-#### - Roof Insp.
Roof nailing on South 2/3 of East wing ....OK
GCB-Courtesy2/25/20152/26/20152/26/2015ADONE
DetailsJim Sly
Larry phone ###-####
Meeting with Plumber.....about Firestopping.
GCB-Courtesy2/24/20152/25/20152/25/2015PDONE
DetailsJim Sly
Larry ###-#### - requested 2p.m.
Would like to discuss mechanical as well
Pre-Construction Conference Met with Dixie Fellows and Mech. contractor. Met with Structural inspectors....Dave Hannah, Phil Shearer, Tony Young. Brought Sam Zahorka plan check for ride along. Architects were also present.
GCB-Fndatn/slab ins/fld vent11/25/201411/26/201411/28/2014PPASS
DetailsDave Hannah
Pete ###-#### - slab/interior footings
GCB-Energy11/25/201411/26/201411/26/2014APART
DetailsDave Hannah
Larry ###-#### - energy compliance: slab on grade for foam north
GCB-Fndatn/slab ins/fld vent11/24/201411/25/201411/25/2014APASS
DetailsDave Hannah
Alvaro ###-#### - requested 9am inspection
GCB-Footing11/18/201411/19/201411/20/2014PPART
DetailsDave Hannah
Alvaro ###-#### - requested appt. at 2p.m.
GCB-Fndatn/slab ins/fld vent11/17/201411/17/201411/17/2014PPEND
DetailsDave Hannah
Alvaro ###-#### - requested 2p.m. appt. to cold to place concrete with outub heat
GCB-Footing11/10/201411/10/201411/12/2014PPEND
DetailsDave Hannah
Alvaro ###-#### spec inspection wii do final sign off of rebar
GCB-Footing11/5/201411/6/201411/6/2014ACANC
DetailsPhil Shearer
Alvaro ###-####
GCB-Stem wall11/6/201411/6/201411/6/2014PPART
DetailsPhil Shearer
Alvaro ###-####
GCB-Footing11/3/201411/3/201411/4/2014PPART
DetailsDave Hannah
Alvaro ###-#### - requested insp. at 2p.m. crew is woking on rebar mti will be on site for spec inspection