Permit NumberGCB14-00135
StatusFinaled
Name D&H Builders
Site Address 5704 MILLSTREAM WAY
Project NameBLD2014-00136
Customer Number 
ePlanReviewNo
Description
**1/5/15 PLAN MODIFICATION TO INCLUDE: FUR UP AND INSULATE EXISTING GARAGE/LIVING SPACE FLOOR PER THE APPROVED PLANS. SRZ** To repair an existing 1,568 square foot, one story, single family dwelling damaged by fire and remodel the 200 sq.ft. of existing garage area to be conditioned living area. Work to include: remove interior non-bearing wall partitions in the old garage area; replace existing west and east walls and their exterior finishes as required; remove and replace select roof trusses damaged by the fire; replace roof shingles and roof sheathing as required; add additional ceiling insulation and floor insulation; and all other repair work per the approved plans, attached plan review report, the structural inspectors final approval, and adopted codes. The Building Official has determined carbon monoxide poisoning, smoke and fire related hazards to be specific hazards associated with buildings and/or structures without smoke and carbon monoxide detection and alarm systems that do not meet current building codes. Carbon monoxide poisoning, smoke and fire related hazards are substantial hazards because the likelihood of death and or injury from said hazards increases in buildings and/or structures. The existing portions of buildings or structures with non-existent or inadequate smoke and carbon monoxide detection and alarm systems that do not meet current building codes must be retrofitted to meet current code requirements. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final1/15/20151/16/20151/16/2015PPASS
DetailsJim Sly
Mike ###-#### - requests 3p.m. insp.
GCB-Energy11/20/201411/21/201411/21/2014APASS
DetailsDave Hannah
Mike ###-####
GCB-Framing11/17/201411/17/201411/17/2014PPASS
DetailsJim Sly
Mike ###-#### - requested call ahead in order to meet at the job site
GCB-Footing10/16/201410/16/201410/16/2014PPASS
DetailsJim Sly
Mike ###-#### house open