GCE-Final | 7/20/2015 | 7/21/2015 | 7/21/2015 | A | PASS |
Rock A. Hudson
|
|
|
Mike ###-#### Added new transfer switch to service and established new service and transfer switch. Bonding done at transfer switch, original mains have separation of neutral and grounds. Final ok
|
GCE-Permanent Service | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Rock A. Hudson
|
|
|
Mike ###-#### p/s u/g rec ok
|
GCE-Final | 7/20/2015 | 7/20/2015 | 7/20/2015 | P | NH |
Rex Boyles
|
|
|
Mike ###-#### no answer to find out what I'm lookin at. UPS building. Spoke to UPS person and they don't know. Left message for Mike. Called twice. As per UPS manager , need to meet with electrician to walk me thru
|