GCM-Final | 9/7/2012 | 9/10/2012 | 9/10/2012 | A | PASS |
Dixie Fellows
|
|
|
Dave @ ###-#### AM inspection requested...signed the card
|
GCM-Final | 8/27/2012 | 8/28/2012 | 8/28/2012 | A | PART |
Dixie Fellows
|
|
|
John @ ###-####...temp occupancy ok...waiting on air balance for nail stations...check equipment on roof
|
GCM-Final | 8/24/2012 | 8/27/2012 | 8/27/2012 | A | NR |
Dixie Fellows
|
|
|
John @ ###-#### partial final....condensate location for mini split in server room?? talked to john about the air balance report for each individual nail station
|
GCM-Final | 8/8/2012 | 8/9/2012 | 8/9/2012 | A | PART |
Dixie Fellows
|
|
|
John @ ###-####
Partial Final requested....ok for partial ceiling cover ...do not cover lobby area or large area to the left of the lobby...need air balance report on nail area ducting
|
GCM-Under Floor | 7/30/2012 | 7/31/2012 | 7/31/2012 | A | PART |
Dixie Fellows
|
|
|
John @ ###-#### Cover inspection requested...this was for lid cover for rooms on east side of building....there wasn't any under floor ducting it was just scheduled for the wrong inspection.
|
GCM-Rough-in | 6/8/2012 | 6/11/2012 | 6/11/2012 | A | PART |
Dixie Fellows
|
|
|
John @ ###-####...ok to cover ducts at nail stations
|
GCM-Pressure Test | 6/1/2012 | 6/4/2012 | 6/4/2012 | A | PASS |
Dixie Fellows
|
|
|
Brandon @ ###-#### ...60lb gas to all equipment drops...all regs will be on roof...all flues on w/h ok
|
GCM-Rough-in | 5/23/2012 | 5/24/2012 | 5/24/2012 | A | PART |
Dixie Fellows
|
|
|
Drew @ ###-####...ok to cover all west walls
|
GCM-Rough-in | 5/17/2012 | 5/18/2012 | 5/18/2012 | A | PART |
Dixie Fellows
|
|
|
John @ ###-####...ok for cover south side of building
|