GCM-Final | 8/15/2014 | 8/15/2014 | 8/18/2014 | P | PASS |
Dixie Fellows
|
|
|
Bryan ###-####..per bill v.
|
GCM-Final | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | NR |
Dixie Fellows
|
|
|
Doug ###-#### please call for access..waiting to hear from the structural inspector if this is a single family dwelling due to my previous correction notice
|
GCM-Final | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PEND |
Dixie Fellows
|
|
|
Doug ###-####..i have sent a conference to the structural inspector as this looks like 2 seperate residences with 2 kitchens, differerent access into units and 2 laundry facilities. the building permit says this is a single family dwelling.
|
GCM-Rough In & Pressure Test | 2/13/2014 | 2/14/2014 | 2/14/2014 | A | PASS |
Dixie Fellows
|
|
|
Sherrie ###-####
|
GCM-Rough In & Pressure Test | 2/12/2014 | 2/12/2014 | 2/12/2014 | P | FAIL |
Dixie Fellows
|
|
|
Sherrie at Idaho Geothermal ###-####..need to used approved glue on pvc flue and re-test..i called and left a message
|
GCM-Rough In & Pressure Test | 2/10/2014 | 2/11/2014 | 2/11/2014 | P | FAIL |
Dixie Fellows
|
|
|
###-#### Idaho Geothermal, New approved manual J on site...posted c/n and called the contractor
|